A hoisting engineering and power distribution room technology, applied in the field of hoisting and maintenance of electric equipment, can solve the problems of personal and property loss, complex working environment, machine crash and death, etc., achieve shortened construction period, good safety, and wide application Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0017] The invention will be described in detail below in conjunction with specific embodiments.
[0018] A super-high-rise power distribution room equipment hoisting engineering construction structure of the present invention includes a load-bearing system, a traction system, a guiding system, and an operating system;
[0019] The load-bearing system includes: a hanging beam 1 arranged between the entrance of the elevator shaft two floors above the floor of the power distribution room and the inspection hole on the opposite side, wherein the hanging beam 1 is perpendicular to the elevator shaft; figure 1 As shown, limited by the site of the elevator shaft, the present invention uses the elevator shaft opening and the opposite inspection hole to erect a hanging beam 1 in the shaft on the upper two floors of the power distribution room floor, and the hanging beam 1 is perpendicular to the shaft opening. In the specific implementation process, because the hanging beam 1 is too h...