A building material transfer device with automatic unloading function
An automatic unloading and transfer device technology, which is applied in the direction of transportation and packaging, conveyor objects, conveyors, etc., can solve the problem of easy damage of prefabricated panels, and achieve the effect of avoiding easy damage
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0029] Such as figure 1 with figure 2 As shown, a building material transport device having an automatic discharge function, comprising a base 1 and a discharge mechanism and a discharge mechanism disposed on the base 1.
[0030] The discharge mechanism includes a horizontal unloading section, an inclined unloading section, and a horizontal discharge section.
[0031] The horizontal discharge section includes two parallel horizontal unloading side plates 2 and a horizontal discharge bottom plate fixed to two horizontal unloading side plates 2, and the two horizontal unloading side panel 2 rotates the connection. There are a plurality of horizontal conveying rollers 21, and the horizontal conveying roller 21 is tightened with a horizontal conveyor belt 22. The base 1 in the horizontal discharge section is mounted on at least two transversely distributed hydraulic cylinders 5, the output rod of the hydraulic cylinder 5 is fixed to the horizontal unloading section of the horizontal u...
specific Embodiment approach
[0038] A prefabricated plate on the truck passes through the horizontal discharge segment, the inclined unloading section and the horizontal discharge section, and finally enters the two sets of synchronous belts 71, and support the prefabricated plate through the boss 710 on the synchronization belt 71. That is, unloading of a prefabricated board.
[0039]Since the unloading of a prefabricated board is completed, the highly decreased the prefabricated plate on the truck, the level of unloading sections and prefabricated plates are no longer flush, not convenient to move the prefabricated board on the truck. On the horizontal discharge section, there is therefore a need for a level of unloading segments in horizontally, so that the horizontal discharge segment is flush with the highest prefabricity. This scheme is arranged in a horizontally unloading section, a tilt unloading section, and a horizontal unloading section to a parallelepiped four-link mechanism. When the level of unl...
Embodiment 2
[0042] The difference from the embodiment is in that: in the present embodiment, a diaphragm is provided on the horizontal discharge section, and the die member includes a die plate located on both sides of the disposal belt 42, and two dials. The plate can convey the belt 42 lateral movement along the horizontal. The prefabricated plate transported on the horizontal unloading section may exist, and the prefabricated plate is positively added to each other by two die plates, so that the prefabricated plate is fixed to each other, and the prefabricated plate can be achieved to ensure the smooth entry of the two sets of synchronization belts. Store between 71.
PUM