High-fill embankment filling construction process
A construction technology and high filling technology, which is applied in the field of building construction technology, can solve the problems of heavy rainfall, inability to meet the properties of soil and stone filling, and poor, and achieve the effect of improving stability.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment
[0030] The embodiment of the present invention provides a high-fill embankment filling construction process, which specifically includes the following processes:
[0031] S1. Substrate treatment: the pavement foundation to be constructed is processed, including the following steps:
[0032] S1-1. Surface cleaning: 0.3m of surface soil such as cultivated soil and miscellaneous filling soil should be removed from the base; if the base is clay, the base should be compacted first; Replace the water-permeable material within 50cm. The water-permeable material can be made of flakes, crushed stones, gravel and other materials with good water stability. Disintegration, solubility and other undesirable properties; replacement fill soil and clear topsoil are prohibited from being piled up randomly, and should be disposed of in the 1# waste slag yard immediately;
[0033] S1-2. Base soil tamping: After the surface cleaning work on the original ground, restore the middle piles and constr...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com