Dewatering and drainage system of subway station open-cut interval foundation pit
Patent Information
- Authority / Receiving Office
- CN Β· China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- CHINA RAILWAY NO 5 ENG GRP
- Publication Date
- 2021-04-23
- Estimated Expiration
- Not applicable Β· inactive patent
Smart Images

Figure 1 
Figure 2
Abstract
Description
technical field
[0001] The invention relates to the technical field of subway construction engineering, in particular to a drainage and drainage system for a foundation pit in an open-cut section of a subway station. Background technique
[0002] During the construction of the subway station, the foundation pit needs to be excavated before the construction of the main structure of the subway station. Before excavation of the foundation pit and during the excavation of the foundation pit, a dewatering well should be constructed first, and the groundwater in the soil layer within the excavation range should be drained in time, so as to facilitate the excavation of the earthwork and help to improve the passive area and excavation area of ββthe enclosure structure. The strength and rigidity of the excavated surface soil ensure the smooth excavation of the foundation pit and the construction of the underground structure to create an anhydrous working condition, including reducing...