[0043] This scheme provides a caisson transportation construction method in a restricted channel, which specifically includes the following steps:
[0044] S1. Carry out pre-shipment preparations for the prefabricated caissons;
[0045] S2. After lifting the caisson to a first predetermined height with a jacking device, install the auxiliary floating airbag on the outer wall of the caisson;
[0046] S3. Transport the lifted caisson to the hoisting area of the wharf by means of a handling device;
[0047] S4. After the hook of the lifting ship drives the spreader to move to the top of the hoisting area, the hanger is lowered so that the height of the spreader is a second predetermined height, and the second predetermined height is used to ensure that the spreader can be connected with the caisson;
[0048] S5. After the sling is connected to the caisson, execute the safety test procedure, and judge whether the safety test procedure is passed, if so, proceed to step S6, other...