Busy trunk line concrete sound barrier installation and construction method

A construction method and concrete technology, applied in the direction of noise absorption device, construction, etc., can solve the problems of difficult installation, lifting of concrete sound-absorbing panels, etc., and achieve the effects of improved construction efficiency, efficient and fast installation operations, and advanced technology.

Inactive Publication Date: 2021-07-30
CHINA RAILWAY SIXTH GRP TAIYUAN RAILWAY CONSTR +1
View PDF13 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] The invention aims to solve the technical problem that the concrete sound-absorbing panels are difficult to lift and install due to the inability to use large machines on both sides of the busy trunk line, and provides a construction method for the installation and construction of the concrete sound barrier on the busy trunk line

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Busy trunk line concrete sound barrier installation and construction method
  • Busy trunk line concrete sound barrier installation and construction method
  • Busy trunk line concrete sound barrier installation and construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0027] refer to Figure 1-Figure 12 , the installation and construction method of a concrete sound barrier for busy trunk lines described in the present invention will be described in detail.

[0028] A construction method for installing a concrete sound barrier on a busy trunk line, comprising the following steps, the process is as follows: figure 1 Shown:

[0029] Step 1: Construct pile foundation 1 at the railway shoulder according to the design position, such as Figure 5 As shown, a number of H-shaped steel columns 3 arranged at intervals and parallel to each other are fixedly connected to the pile foundation 1 through the embedded parts 2, and the H-shaped steel columns 3 are located in the vertical direction, such as Figure 7 As shown; the H-shaped steel column 3 is made of H-shaped steel. According to the design requirements, the standard span of the adjacent embedded part 2 is 4m, and the error is -10~+20mm, because under normal circumstances, the length of the sta...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention belongs to the technical field of railway trunk line sound barrier installation, relates to installation of concrete acoustic boards, in particular to a busy trunk line concrete sound barrier installation and construction method, and solves the technical problems in the background technology. According to the construction method, the H-shaped steel stand columns and the right triangle supporting frames are used as rail supports, the rail is erected on the side away from the existing railway, the hoisting moving trolley and the transporting trolley are arranged on the rail, and the concrete acoustic board is transported and hoisted through the ra By means of the construction method, the concrete acoustic board is fast and convenient to install, the problem that large machines and tools cannot be used on an existing operation line is solved, interference to the existing operation line is avoided, installation work can be efficiently and fast completed under the condition that transportation is not interrupted, the construction efficiency is remarkably improved, the technology is advanced, and the construction cost is reduced. Obvious social benefits and economic benefits are obtained.

Description

technical field [0001] The invention belongs to the technical field of installing sound barriers on railway trunk lines, and relates to the installation of concrete sound-absorbing panels, in particular to a method for installing and constructing concrete sound barriers on busy trunk lines. Background technique [0002] With the gradual improvement of the economic level, people's living conditions have been significantly improved, and the daily travel methods have also shown diversified development, and strict standards have been put forward for transportation. The transportation sector has promoted the development process of the transportation industry through continuous technological innovation and exploration. Railway is an indispensable means of transportation. [0003] Most of the non-electrified railways have been built for a long time. At the beginning of construction, there were no corresponding environmental protection measures or the measures were not perfect. Wit...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E01F8/00
CPCE01F8/0005E01F8/0017E01F8/0023
Inventor 张永超孔彪杨思宏张建立管博侯晓飞刘宝超刘扬周智王涛
Owner CHINA RAILWAY SIXTH GRP TAIYUAN RAILWAY CONSTR
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products