Construction method for building and installing light steel portable house

A technology for a prefab house and a construction method, which is applied in building structures, buildings, signal devices, etc., can solve the problem of inconvenient installation of external wall panels, improve installation accuracy and installation quality, improve installation quality, and reduce installation difficulty. Effect

Active Publication Date: 2021-11-05
华济建设工程集团有限公司
View PDF9 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] In order to improve the problem of inconvenient installation of exterior wall boards, this application provides a construction method for the construction and installation of light steel prefabricated houses

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for building and installing light steel portable house
  • Construction method for building and installing light steel portable house
  • Construction method for building and installing light steel portable house

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0050] The following is attached Figure 1-7 The application is described in further detail.

[0051] The embodiment of the application discloses a method for constructing, installing, and constructing a light steel prefabricated house. refer to figure 1 , the construction and installation method of the light steel prefabricated house includes the following steps,

[0052] S1. Base plate 1 installation: clean the ground area where the light steel prefabricated house is installed, and adjust the base plate 1 to a horizontal state with the assistance of the level bubble, and fix the base plate 1 on the ground;

[0053] S2. Assembling the column 3 and the exterior wall panel 2: fitting and fixing the exterior wall panel 2 between the adjacent columns 3;

[0054] S3. Installation of the column 3 and the exterior wall panel 2: accurately adjust the column 3 and the exterior wall panel 2 to a vertical state through the construction auxiliary device, and fix the column 3 on the bo...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method for building and installing a light steel portable house. The construction method comprises the following steps that a bottom plate is installed, specifically, the bottom plate is adjusted to be in a horizontal state, and the bottom plate is fixed to the ground; stand columns and outer wall plates are assembled, specifically, the outer wall plates are embedded and fixed between the adjacent stand columns; the stand columns and the outer wall plates are installed: specifically, the stand columns and the outer wall plates are precisely adjusted to be in a vertical state through a construction auxiliary device, the stand columns are fixed to the bottom plate, and gaps are sealed; herringbone beams and purlines are installed, specifically, the herringbone beams are fixed to the tops of the stand columns, and the purlines are fixed to the herringbone beams; roof plates are installed, specifically, the roof plates are buckled and fixed in a steel structure composed of the herringbone beams, the purlines and the stand columns, and gaps are sealed; and a door and a window are installed, specifically, the door and the window are buckled and fixed to the outer wall plates, and gaps are sealed. The method has the effect of facilitating installation of the outer wall plates, the outer wall plates can be stably kept in the vertical state, and the installation quality of the light steel portable house can be improved.

Description

technical field [0001] The invention relates to the field of assembly of building components, in particular to a method for constructing and installing a light steel prefabricated house. Background technique [0002] The light steel prefabricated house is a new concept of environmentally friendly and economical prefabricated houses with light steel as the skeleton, sandwich panels as the enclosure material, and standard module series for space combination. The components are connected by bolts. Because the light steel prefabricated house can be assembled and disassembled conveniently and quickly, it is often used in various construction sites as office migrant worker dormitories, and can also be used for flat roofs and storeys, various warehouses, etc. [0003] The Chinese patent with the application number CN202011452519.5 in the related technology proposes a method for the construction, installation and construction of a light steel prefabricated house, which specifically ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E04G21/16E04G21/18E04B1/343G01C15/12G08B21/24G08B5/36
CPCE04G21/16E04G21/162E04G21/167E04G21/1841E04B1/34315E04B1/34384G01C15/12G08B21/24G08B5/36
Inventor 蔡贤玮李浩梁友清孙贝贝姚刚任虹陈帅余海勤李华庄凯喆
Owner 华济建设工程集团有限公司