Unlock instant, AI-driven research and patent intelligence for your innovation.

Active control grouting lifting method for subway station close-fitting and under-penetrating existing station

A technology of grouting lifting and existing stations, which is applied to underwater structures, infrastructure tests, construction, etc., can solve the problems of existing stations, settlement values ​​exceeding control values, etc., and achieve the effect of simple operation

Active Publication Date: 2022-07-01
DALIAN JIAOTONG UNIVERSITY
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, even though the hole pile method is used for construction, the settlement value of the existing station may still exceed the control value during the construction process. At this time, the construction will face huge risks and have a serious impact on the existing station

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Active control grouting lifting method for subway station close-fitting and under-penetrating existing station
  • Active control grouting lifting method for subway station close-fitting and under-penetrating existing station
  • Active control grouting lifting method for subway station close-fitting and under-penetrating existing station

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0040]The newly built subway station in the embodiment of the present invention adopts the eight-guided-hole pile method for construction, and the distance between the top plate of the new station and the bottom plate of the existing station is 0.5m.

[0041] like figure 1 As shown in the embodiment of the present invention, the method for actively controlling the grouting lifting method for constructing a subway station by the hole-piling method and passing through the existing station closely, including the following steps:

[0042] S1: Construction preparation: Before construction, according to the actual site data, the position of the pilot hole, the relative position of the existing station and the new station, the position of the deformation joint of the existing station, and the main impact area of ​​the close-fitting underpass construction on the existing station, the notes are compiled. The grouting lifting scheme. In this embodiment, the grouting lifting scheme inclu...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses an active control grouting lifting method for a subway station to be closely attached to an existing station, including construction preparation, grouting hole arrangement, grouting stop wall setting, grouting lifting and grouting effect inspection. According to the actual site data, the position of the pilot hole, the relative position of the existing station and the new station, the position of the deformation joint of the existing station, and the main impact area of ​​the close-fitting underpass construction on the existing station, the grouting lifting plan is prepared, and then the Deep hole grouting forms a grouting wall. After the grouting wall is formed, sleeve valve pipe grouting is used to raise the existing station. After the excavation of the pilot hole is completed, the grouting effect shall be checked, and repeated grouting shall be carried out for individual parts with large settlement values. Ensure that the settlement is controlled within a controllable range. This method can actively control the settlement and deformation of the existing station when the new station is closely attached to the existing station by the hole pile method, so that the construction of the underpass can be completed under the normal operation conditions of the existing station, ensuring that the existing station and the densely attached under the existing station are completed. Wear construction safety.

Description

technical field [0001] The invention belongs to the technical field of underground structure construction, and relates to an active control grouting lifting method for subway stations that are closely attached and penetrated through existing stations, in particular to an actively controlled grouting lifting method of tunnel pile method construction of subway stations that are closely attached and penetrated through existing stations. Background technique [0002] In recent years, rail transit has begun to develop three-dimensionally, and the concept of underground three-dimensional intercommunication has been established in the design concept of tunnels and underground works, which has gradually increased the number of projects that cross existing lines. For the current domestic and foreign closely attached and underpassed projects, mainly new tunnels are closely attached to underpass existing tunnels or existing station projects, and newly built stations are closely attached...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D29/045E02D29/16E02D15/04E02D33/00
CPCE02D29/045E02D29/04E02D29/16E02D15/04E02D33/00E02D2250/0023
Inventor 王海涛许明杨张志伟刘国龙尤强张顶立王忠昶何历超
Owner DALIAN JIAOTONG UNIVERSITY