Engineering construction progress plan management system based on BIM

A schedule planning and management system technology, applied in the field of engineering construction, can solve problems such as poor accuracy of 3D models, affect the construction process, and inability to compare, so as to avoid the stagnation of construction progress

Pending Publication Date: 2022-02-18
CHONGQING UNIV
View PDF0 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] However, when the current BIM technology is used for scanning modeling, due to the lack of redundancy and noise reduction in the scanned data, the efficiency of building complex buildings is low, and the accuracy of the 3D model is poor. It is impossible to compare the project construction progress plan with the actual construction model, resulting in the actual construction exceeding the pre-plan, resulting in insufficient construction materials and large changes in the construction period. It is impossible to remind the staff to prepare in time and affect the subsequent construction process. In view of this, We propose a BIM-based engineering construction schedule management system

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Engineering construction progress plan management system based on BIM
  • Engineering construction progress plan management system based on BIM
  • Engineering construction progress plan management system based on BIM

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0049] see Figure 1-Figure 4 As shown, this embodiment provides a BIM-based engineering construction schedule management system, including a schedule compilation unit 100, a BIM schedule tracking unit 200, and a model comparison unit 300;

[0050] The progress plan preparation unit 100 is used for pre-designing the project construction plan, and preparing the three-dimensional model diagram of the project construction plan;

[0051] In this embodiment, the schedule preparation unit 100 includes a construction scheme setting module, a model preparation module and a construction material recording module;

[0052] The construction plan setting module is used to design the construction plan of the engineering construction;

[0053] The model compilation module is used to construct the renderings according to the construction plan, and generate the three-dimensional model diagram of the plan, so as to facilitate a more intuitive understanding of the construction plan;

[0054] ...

Embodiment 2

[0082] Considering that when the project construction exceeds the expected plan, the materials and construction period cannot be updated in time, which will affect the subsequent normal construction progress. The difference between this embodiment and Embodiment 1 is that:

[0083] The schedule preparation unit 100 also includes a plan optimization module, the plan optimization module is used to receive the signal reminding the staff from the remote interaction module, and adjust the content of the remote interaction module according to the on-site three-dimensional model;

[0084]The plan optimization module can realize the modification of the content recorded in the construction material recording module, and use Transact-SQL statements such as INSERT, DELETE and UPDATE to add, delete or change information in the database of the construction material recording module, so that according to the actual project The construction is carried out to adjust the construction materials,...

Embodiment 3

[0087] Considering that the data scanned by the 3D laser scanner is redundant and takes up a large space, resulting in unsmooth modeling, which is not conducive to the accuracy of the modeling of the model building module, so cloud processing is performed before the model is built. This embodiment and implementation Example 1 differs in that:

[0088] The model building model also includes cloud processing redundancy elimination algorithm, including the following steps:

[0089] Point cloud splicing, unifies the coordinates of the data points scanned by the 3D laser scanner, takes the scanning station as the benchmark, and unifies the scanned images of other stations into the coordinate system of the reference station through the forced addition of points with the same name;

[0090] Data redundancy is used to uniformly identify building characteristic range values ​​through data point coordinates, reduce the amount of data points on the basis of maintaining model accuracy, an...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to the technical field of engineering construction, in particular to an engineering construction progress plan management system based on BIM. The system comprises a progress planning unit, a BIM progress tracking unit and a model comparison unit. The progress plan compiling unit is used for compiling a plan three-dimensional model diagram of engineering construction; the BIM progress tracking unit is used for establishing a field three-dimensional model diagram; and the model comparison unit is used for comparing the planning three-dimensional model diagram of the progress planning unit with the field three-dimensional model diagram of the BIM progress tracking unit, calculating the similarity, and feeding back when the similarity is smaller than a comparison threshold. Feedback is carried out when the comparison threshold value is exceeded, so that a worker can timely know the progress of an engineering site. Meanwhile, the deviation condition between engineering site construction and a plan can be determined according to the similarity, adjustment and preparation of construction materials can be conveniently and timely made, and the situation that the construction progress is stopped due to insufficient materials caused by large plan deviation is avoided.

Description

technical field [0001] The invention relates to the technical field of engineering construction, in particular to a BIM-based engineering construction schedule management system. Background technique [0002] Engineering construction is the basic economic activity for the occurrence and development of human civilization, which directly has an important impact on the political, economic, cultural, military and other activities of human society. In the process of construction, by using advanced technology, the quality and level of management can be improved, and the good implementation of construction projects can be realized. Among them, BIM technology is widely used in the construction industry today. Its main It is a technology with three-dimensional modeling technology as the core. By applying it to the control of the construction progress of the construction project, it is possible to understand the construction progress of the construction project in a timely manner, and...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): G06Q10/10G06Q50/16G06T17/00G06F30/13
CPCG06Q10/103G06Q50/165G06F30/13G06T17/00G06T2210/61
Inventor 罗勇军张巍
Owner CHONGQING UNIV