Building construction method and system

A building construction and construction technology, applied in the field of building construction methods and systems, can solve problems such as camera deviation of building results, and achieve the effect of correcting building errors

Pending Publication Date: 2022-03-15
上海集盛装饰工程有限公司
View PDF0 Cites 1 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] During building construction, existing technologies often carry out artificial planning and construction. Due to manual operations, there are often some errors, resulting in some deviations between the final building result and the initial camera. By spotting deviations when they occur, you can prevent them from happening

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Building construction method and system
  • Building construction method and system

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0030] A method of building construction, said method performing the following steps:

[0031] Step 1: receiving an instruction to select a building area; acquiring building data corresponding to the selected building area;

[0032] Step 2: converting the building data into a local space, and generating a building model according to the converted local space;

[0033] Step 3: According to the generated model, build a prefabricated monolithic reinforced concrete load-bearing wall;

[0034] Step 4: After the slab is solidified in the first step of the load-bearing wall, generate a new model according to the load-bearing wall of the building, and compare it with the model generated in step 2. If the comparison passes, go to step 5; if the comparison fails, then Issue a prompt message;

[0035] Step 5: The surveyor puts the position dimension line of the precast concrete load-bearing wall component; makes a concrete pad at the position of the upper wall component of the precast ...

Embodiment 2

[0039]On the basis of the previous embodiment, in the step 2: convert the building data into a local space, and according to the converted local space, the method for generating a building model performs the following steps: convert the building data into a local space ; forming a surface mesh from the transformed architectural data; generating at least one side surface at an angle relative to the surface mesh; combining the at least one side surface with the surface mesh to generate a model.

[0040] The standardization of building construction is to obtain the best order within a certain range, and to formulate the common use and repeated use of the actual problems or potential problems. The standardization of construction project management refers to the transformation of project management from extensive to institutionalized, standardized and standardized by duplicating the successful practices and experiences of project management in the same or similar management modules....

Embodiment 3

[0042] On the basis of the previous embodiment, in the step 2: convert the building data into a local space, and according to the converted local space, the method for generating a building model performs the following steps: including the following steps: according to the acquired building data , generate an image of the building, and calculate the depth map corresponding to the depth of the image pixel in the space according to the generated image; calculate the resolution map corresponding to the resolution of the image pixel for the image according to the depth map; by converting the current image Pixels are projected to other images so that the current image pixels match another sequence image pixel; a pixel of the current image is selected based on its resolution and the resolution of other sequence image pixels that match this pixel; a model is built based on the selected pixels.

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a building construction method and system. The method comprises the following steps: step 1, receiving an instruction to select a building area; obtaining building data corresponding to the selected building area; 2, converting the building data into a local space, and generating a model of the building according to the converted local space; 3, according to the generated model, the prefabricated and assembled integral type reinforced concrete bearing wall is built; 4, after the first-step plate of the load bearing wall is condensed, a new model is generated according to the load bearing wall of the building and compared with the model generated in the step 2, and if the comparison is passed, the step 5 is executed; if not, prompt information is sent out; step 5, placing a position dimension line of the prefabricated concrete bearing wall component by a measurer; a concrete cushion block is manufactured at the position of an upper wall component of the prefabricated concrete bearing wall component; by generating the model in the building process in real time and comparing the model with the original model, building errors are corrected in real time, and it is guaranteed that the final result meets the expectation.

Description

technical field [0001] The invention relates to the technical field of building engineering, in particular to a building construction method and system. Background technique [0002] Building construction refers to the production activities in the implementation stage of engineering construction. It is the construction process of various buildings. It can also be said to be the process of turning various lines on the design drawings into real objects at designated locations. It includes basic engineering construction, main structure construction, roofing engineering construction, decoration engineering construction, etc. The place where the construction works is called "construction site" or "construction site", also called construction site. [0003] Building construction is a production process that people use various building materials and mechanical equipment to build various building products in a certain space and time according to a specific design blueprint. It inc...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): G06F30/13G06Q10/06G06Q50/08E04G21/00
CPCG06F30/13G06Q10/06313G06Q50/08E04G21/00
Inventor 尤冯同
Owner 上海集盛装饰工程有限公司