Project progress tracking method, system and device and computer readable medium
A project progress and project technology, applied in project progress tracking methods, devices, computer readable media, and system fields, can solve problems such as inaccurate tracking of project progress, and achieve the goal of improving project tracking efficiency, reducing workload, and improving accuracy Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0056] Such as figure 2 As shown, one of the embodiments of the present invention discloses a project progress tracking method, comprising the following steps:
[0057] Step S100, acquiring construction site images;
[0058] Specifically, in this step, the construction worker obtains the construction site image through the acquisition terminal 1, wherein the construction site image is the site under construction in the project plan of the day, for example, in the project plan of the day, Room 102, Building 12 of a community If the interior wall needs to be painted, the construction site is Room 102, Building 12 of the community, and the construction site image includes the image information of the inner cavity painted on that day;
[0059] As a preferred implementation in this embodiment, the construction site image is an image of the work results produced by the work of building walls, installing steel mesh, pouring concrete, painting interior walls, painting exterior walls, ...
Embodiment 2
[0091] As a further embodiment of the present invention, the project progress tracking method also includes:
[0092] Step S400, for a project whose completion degree reaches a preset value, send a notification message to the corresponding construction management personnel to notify them to conduct quality inspection of the project;
[0093] Specifically, in this embodiment, the sum of the project completion degree of the day in history is counted, and when the sum of the project completion degree of the day in history is greater than or equal to the preset value, the corresponding construction management personnel are notified to initiate the quality acceptance process;
[0094] In some examples, the preset value may be 100% or 96%;
[0095] As a preferred implementation in this embodiment, for construction projects that fail the quality inspection, it is necessary to issue a rectification plan and rectify according to the rectification plan, wherein, such as Figure 6 As sh...
Embodiment 3
[0106] The present invention also discloses a project progress tracking system, the system 500 includes:
[0107] An acquisition unit 501, configured to acquire construction site image information;
[0108] A project plan management unit 502, configured to generate a project plan;
[0109] An image recognition unit 503, configured to generate project construction quantities according to construction site images;
[0110] A comparison unit 504, configured to compare project plans and project construction quantities to generate project completion;
[0111] The alarm unit 505 is configured to send alarm information to notify the construction management personnel corresponding to the project that has reached the preset completion degree of the project.
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com