Model test device and method for research on water-induced degradation of rock slope
A model test device and rock slope technology, applied in the field of rock and soil mechanics, can solve the problems of long test period, slow water-rock interaction, and ignoring the effect of water on rock deterioration, so as to reduce the time of water degradation and shorten the test the effect of time
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
like figure 1 As shown, this embodiment provides a model test device 100 for the study of water-induced degradation of rock slopes, including a stress loading device 1, a crack propagation detection device 2 and a water injection device 3, and the stress loading device 1 is used for setting in the rock slope Above the rock slope model sample 7, the crack propagation detection device 2 is used to be arranged on the rock slope model sample 7. The upper end of the rock slope model sample 7 is provided with an upper end crack 4, and the upper end crack 4 is connected to the horizontal plane. There is an included angle between them, the stress loading device 1 can stress load the rock slope model sample 7, and the crack propagation detection device 2 is used to detect whether the rock slope model sample 7 enters the stage of unstable crack propagation, and water injection The device 3 is used to inject liquid into the upper crack 4 . Among them, the stress loading device 1 is prefe...
Embodiment 2
The present embodiment provides a method for research on water-induced degradation of rock slopes, including:
S1. Obtain a rock slope model sample 7, and install a crack propagation detection device 2 on the rock slope model sample 7; the upper end of the rock slope model sample 7 is provided with an upper end crack 4, and the upper end crack 4 is connected to the horizontal plane. There is an included angle between them; preferably, S1 includes: (1) Determining the size of the model and the construction plan, specifically, using the same or similar materials as the rock slope material, combined with the built model test plan, to prepare the rock slope Model sample 7; (2) Complete the model building and installation of monitoring equipment, including at least the fixation of rock slope model sample 7, the fixation of stress loading device 1 and the fixation of crack propagation detection device 2.
[0028] S2. Perform stress loading on the rock slope model sample 7, and the cr...