Hydroelectric units black start-up ability verification test method
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- 四川中鼎科技有限公司
- Publication Date
- 2008-10-22
Abstract
Description
technical field
[0001] The invention relates to a test method for verifying the black start capability of a hydroelectric generating set in a hydroelectric power plant under the condition of a power grid accident and unexpected power outage. Background technique
[0002] Black start means that after the entire power grid or a certain power grid collapses and shuts down due to a fault, the system is completely powered off and is in a "black" state. capacity, gradually expand the scope of system recovery, and finally achieve the recovery and power supply of the entire system.
[0003] The black start of the hydroelectric unit refers to the use of the characteristics of the hydroelectric unit to complete the self-start of the unit in the case of the disappearance of the plant AC power and the opening of the water inlet gate, or to use the emergency backup power of the hydropower station (station) (such as a diesel generator, etc.) to start the water inlet Gate and restore the ...