A concrete and piling technology, applied in sheet pile wall, foundation structure engineering, construction, etc., can solve the problems of cumbersome construction, speed up the progress of the project, and use more materials, and achieve the goal of reducing the difficulty of construction, speeding up the construction period, and reducing the cost. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0046] like figure 2 As shown, a pile-forming device for manufacturing tube-plate joint piles includes a tube-pile pile-forming device 201. A vertical sheet pile forming device 202 is welded on the upper side of the outer tube cylinder. The sheet pile forming device 202 is a plate body with a U-shaped cross section. The free opening end of the sheet pile forming device 202 is welded on the barrel pile. On the upper side of the outer tube cylinder of the pile forming device 201, the central plane of the sheet pile forming device 202 and the axis of the cylindrical pile forming device 201 are in the same plane, and the height of the sheet pile forming device 202 is smaller than that of the cylindrical pile forming device 201 height, the top surface of the sheet pile forming device 202 is flush with the top surface of the cylindrical pile forming device 201, and the first pile tip 203 is installed at the bottom of the cylindrical pile forming device 201. The structure of the fir...
Embodiment 2
[0056] In use, the difference from Embodiment 1 is that the strip plate 205 at the bottom of the sheet pile forming device 202 is squeezed by the soil during the sinking process, and is in a closed state, and the soil is discharged to both sides, without It will enter the pile-forming space, and in the process of pulling up, it is in an open state due to the extrusion of concrete, so that piles can be formed smoothly.
[0057] Example 3:
Embodiment 3
[0059] The difference between the pile forming device in the present embodiment 3 and the embodiment 1 is: as Figure 11 As shown, the second pile point 204 is not a triangular prism, but includes two strip plates 205 and a triangular pyramid frustum that is placed horizontally on one side of the two strip plates 205 and has a point downward. The upper end faces of the strip plates 205 are respectively hinged with the two opposite end faces at the bottom of the sheet pile forming device 202, and the lower ends of the two strip plates 205 are overlapped together to form a V-shaped structure in the longitudinal section. The two strip plates 205 The same end face of the same side of the triangular pyramid body is seamlessly fitted with the smaller end face of the triangular pyramid body, and the other end faces of the two strip plates 205 are all connected to the end face of the sheet pile forming device 202 which is far away from the tube pile forming device 201. The sides are s...