Congestion control method and system for machine type communication (MTC) equipment
A machine-type communication and congestion control technology, applied in wireless communication, access restriction, connection management, etc., can solve the problem of affecting the signaling processing speed of the connected equipment, and affecting the efficiency and quality of terminal services connected to the network by the core network. , huge and other problems, to avoid the effect of service efficiency and quality
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0028] Such as figure 2 shown, including:
[0029] Step 10, the mobility management unit (MME) sends overload control signaling to the base station when it is overloaded, and the overload control signaling is used to instruct the base station to perform load control;
[0030] When the MME is overloaded, it means that the current load of the MME reaches or exceeds the set threshold.
[0031] The overload control signaling may include a waiting time, or include a waiting time and a category of terminals that need to be controlled.
[0032] Step 20: After receiving the overload control signaling, the base station rejects the terminal's request for establishing a radio resource control (Radio Resource Control, RRC for short) connection according to the overload control signaling.
[0033] Only after receiving the overload control signaling, the base station performs connection control on the subsequently received RRC connection establishment request.
[0034] If the overload c...
Embodiment 2
[0045] Step 20, setting a threshold value Th for judging overload for the mobility management unit (MME);
[0046] The threshold may be a percentage, expressed as a percentage of the maximum processing capacity of the MME.
[0047] Step 21, when the current load of the MME reaches the set threshold value Th, the MME sends the overload control signaling "OVERLOAD START" to the base station, which is used to instruct the base station to perform load control, wherein the "OVERLOAD START" signaling includes : 1) Terminal category that needs to be rejected; 2) Waiting time;
[0048] If there are multiple categories that need to be rejected, the information in the signaling can be that each category corresponds to a waiting time, as shown in the following structure:
[0049] Category 1: waiting time 1;
[0050] Category 2: waiting time 2;
[0051] Category 3: waiting time 3;
[0052] It can also be that all categories correspond to the same waiting time, as shown in the followin...
Embodiment 3
[0061] Step 30, setting a threshold value Th for judging overload for the mobility management unit (MME);
[0062] Step 31, when the current load of the MME reaches the set threshold value Th, the MME sends the overload control signaling "OVERLOAD START" to the base station, which is used to instruct the base station to perform load control, wherein the "OVERLOAD START" signaling includes :waiting time;
[0063] In this embodiment, the OVERLOAD START signaling does not include the types of terminals that need to be rejected, and the base station rejects all signaling RRC connection establishment.
[0064] Step 32, after the base station receives the "OVERLOAD START" signaling, the base station sets a delay time, which is used to indicate the time when the rejected terminal sends the RRC connection establishment request next time;
[0065] Step 33, when the terminal requests to establish an RRC connection, the base station rejects the RRC connection establishment of all termin...