Construction method for protecting partition wall in double-arch tunnel through temporary support of middle pilot tunnel
A technology of temporary support and construction method, which is applied in tunnels, tunnel linings, earthwork drilling and mining, etc., to achieve the effect of saving materials and reducing costs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0017] A construction method for protecting the middle partition wall of a multi-arch tunnel by using the temporary support of the middle pilot tunnel of the present invention will be further described below in conjunction with the embodiment.
[0018] The process and steps adopted by a construction method of the present invention that utilizes the temporary support of the pilot tunnel to protect the middle partition wall of the multi-arch tunnel are:
[0019] The first step: Excavate the pilot tunnel, and construct the temporary support for the pilot tunnel according to the design requirements. The support form adopts bolts, hanging steel mesh, sprayed concrete and I14 I-shaped steel arch joint support. The length is 2.5-3.5m, and the radial spacing is 1.5-2.5m; the steel mesh uses Φ8 steel mesh, the mesh size is 20×20cm; the shotcrete is marked C20, and the thickness is 20cm; I-beams, with a spacing of 1.00m / trunk, I14-type I-beams for V-grade surrounding rock, with a spaci...
PUM
Login to View More Abstract
Description
Claims