[0020] Such as figure 1 As shown, a row of φ0.2~0.6cm steel column 1 is fixed between the beam, ceiling (floor) and floor (floor) of the frame structure building, and a φ0.2~0.6cm steel bar is fixed between the frame wall and the column 2. Put the A-type concrete light brick 3 coated with cement glue on the joint surface, put it on the column 1 and the cross bar 2 through the groove 4 of the reinforcement, and fill the groove 4 of the reinforcement with expansion cement to form the first One layer; the A-shaped bricks 3 are put on the column 1 one by one, and at the same time, they are bonded with the first layer of bricks by cement glue, and the grooves 4 are poured with expansive cement to form the second layer; Frame the wall, fix the crossbar 2 between the uprights, put the A-shaped brick 3 on the upright 1 and the crossbar 2, and glue the bricks together with cement glue, and pour the expanded cement slurry into the rib groove 4 to form the first Three floors are built ...
Embodiment 2
[0022] Such as figure 2 As shown, a row of φ0.2~0.6cm reinforced columns 1 is fixed between the beams, ceiling (floor) and floor (floor), and a φ0.2~0.6cm reinforced bar 2 is fixed between the frame walls and columns, Tighten the intersection of the column 1 and the cross bar 2 with iron wires, put the B-type light brick 3 on the column 1 and the cross bar 2 successively relying on the reinforcement groove 4, and glue the bricks to each other with cement glue. After one layer, use expansive cement slurry to pour through the rib-through groove 4, fix the second cross bar 2, and then pass through the B-shaped bricks 3 one by one. Go through the reinforcement groove 4 and build the second layer. According to this step, add rods, bricks, and grout layer by layer until the beams and ceilings (floors). Afterwards, seal the filling port 5 and all joints with caulking glue, and then paint the paint.
Embodiment 3
[0024] Such as image 3 As shown, first fix two rows of φ0.2~0.6cm reinforced columns 1 between the beams, ceiling (floor) and floor (floor), and fix two φ0.2~0.6cm reinforced bars between the frame walls and columns 2. Tighten the intersection of the column 1 and the cross bar 2 with iron wire, put the light concrete C-shaped brick 3 through the semi-cylindrical groove 4 with a width of 4cm and a depth of 2cm, and put it on the column 1 and the cross bar one by one 2, the bricks are closely bonded with cement glue, and after the bricks are built, the expansion cement is poured into the rib penetration groove 4, and the C-shaped bricks 3 are put on the column 1 piece by piece, and the bricks are also built with cement glue After laying the second layer of bricks, place two steel crossbars 2 on it so that they fit into the grooves 4 of the C-shaped bricks 3, and then pour the expanded cement slurry into the ribs. Groove 4, so that the rods are fixed layer by layer, bricks are ...