A technology of gas pressure regulator and experimental method, which is applied in the direction of measuring device, machine/structural component test, instrument, etc., which can solve the problem of not enough to explain the reliable life of parts, it is impossible to explain the service life, and it is not enough to characterize the reliability of operation, etc. problems, to achieve the effect of high correlation, strengthening influencing factors, and high operational reliability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
specific experiment approach 1
[0028] 1) Fix the gas pressure regulator 1 under test in the thermostat 2;
[0029] 2) Seal the inlet of the gas pressure regulator under test with a blind plate, and connect the outlet of the gas pressure regulator under test to the inlet and outlet of the experimental system pipe 12 of the experimental device at the same time with a metal hose;
[0030] 3) Use a vacuum pump to evacuate the test piping system and check the airtightness;
[0031]4) After passing the air tightness inspection, open the test gas medium gas tank 7, inject the test medium into the test system through the test gas medium injection port 8, and close the test gas medium injection port when the system pressure reaches the maximum test pressure 8 valves, stop inflation.
[0032] 5) Start the thermostat 2 to run, so that the temperature reaches the preset test temperature and stabilizes for a period of time;
[0033] 6) Turn on the circulating compressor, start the programmable controller 4, and both t...
specific experiment approach 2
[0040] 1) Fix the gas pressure regulator 1 under test in the thermostat 2;
[0041] 2) Connect the metal hose for the inlet and outlet of the gas pressure regulator under test to the inlet and outlet of the experimental system pipe 12 of the experimental device respectively;
[0042] 3) Use a vacuum pump to evacuate the test piping system and check the airtightness;
[0043] 4) After passing the air tightness inspection, open the gas tank 7 for the test gas medium, inject the test medium into the test system through the gas medium injection port 8 for the test, and when the system pressure reaches the closing pressure of the gas pressure regulator 1 under test, Close the valve of the gas medium injection port 8 for the test, and stop the inflation.
[0044] 5) Start the thermostat 2 to run, so that the temperature reaches the preset test temperature and stabilizes for a period of time;
[0045] 6) Turn on the circulating compressor, start the programmable controller 4, and t...