Construction process for implementing post-cast strip casting by post-cast strip stiff steel pipe support system
A technology of steel pipe support and construction technology, which is applied in the processing of building materials, construction, building construction, etc., and can solve the problem of affecting the construction progress of formwork removal, plastering, secondary structure, decoration, etc., and the inability to use the unloading platform and the atrium Problems such as the discharge and feed of the hole to achieve the effect of shortening the construction period, saving rental costs, and fast operation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0025] 1. Preparation of cylindrical straight rigid steel pipe:
[0026] One end of each cylindrical straight rigid steel pipe is sealed to the steel plate.
[0027] 2. Construction steps:
[0028] 1. Open two rows of openings on the laid beam bottom formwork. Each row of openings is arranged on both sides of the post-casting belt and controlled in the same row of openings. The distance between adjacent openings shall not exceed 4m.
[0029] 2. Put a straight rigid steel pipe in each hole (such as figure 2 As shown), the sealed end of the steel plate faces upward, and the lower end of each straight rigid steel pipe is supported by a steel pad with a height of not more than 40mm (such as image 3 As shown), make the upper end face of each straight stiffened steel pipe flush with the upper plane of the beam bottom formwork, and adjust each straight stiffened steel pipe to be perpendicular to the ground.
[0030] 3. Use long steel pipes to pull them vertically and hor...