Power load control method and system
A technology of power load and control method, applied in the direction of power network operating system integration, information technology support system, electrical components, etc., can solve the problems of large amount of information processed by the server and insufficient processing capacity, so as to overcome the increase of information amount and reduce the burden of information Dealing with Burden Effects
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0052] Based on the first embodiment, the second embodiment of the present invention discloses yet another electric load control method, wherein, for the same working principle, refer to the corresponding drawings and descriptions of the first embodiment, and will not be repeated here.
[0053] see image 3 , the method also includes:
[0054] Step 301: The current load control terminal receives the second control instruction issued by the server or forwarded by the upper-level load control terminal, and the second control instruction instructs the current load control terminal to collect second power consumption information;
[0055] When the current load control terminal is a first-level load control terminal, it directly receives the second control instruction issued by the server; A second control instruction that is directly forwarded; the second control instruction instructs the current load control terminal to directly collect the respective power consumption informati...
Embodiment 2
[0063] Based on Embodiment 2, Embodiment 3 of the present invention discloses yet another electric load control method, wherein, for the same working principle, refer to the corresponding drawings and descriptions of Embodiment 2, and will not repeat them here.
[0064] The method also includes:
[0065] Construct the hierarchical distribution relationship of negative control terminals, including:
[0066] At least two levels of load control terminals are set up, the first level load control terminal receives the control command from the server, and returns the electricity consumption information collected from the second level load control terminal and the first level load control terminal directly from the Power consumption information collected by on-site loads;