A construction method and technology for hollow piers, which are used in the erection/assembly of bridges, bridges, buildings, etc., can solve the problems of narrow interior space of hollow piers, high requirements for support stability, and reduced formwork turnover rate. Save construction period and have strong manufacturability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0030] The present invention is described below in the form of specific examples, but the present invention is by no means limited to the following examples.
[0031] A hollow pier capping construction method, such as Figure 1-2 , Shown in 6, described hollow pier capping construction method comprises the following steps:
[0032] 1. Prefabricated roof capping plate 1;
[0033] 2. Construction of the pier wall 2 of the hollow pier, strengthening the self-chamfering 3 reinforcement arrangement at the top of the hollow pier;
[0034] 3. When the concrete strength of the hollow pier pier wall 2 reaches more than 75%, hoist the prefabricated capping cover plate 1;
[0035] 4. Close the gap of the prefabricated roofing cover plate 1 with mortar;
[0036] 5. Carry out the concrete pouring construction of pallets and top hats, including binding pallets, top hat steel bars and concrete pouring;
[0037] Sixth, the hollow pier capping construction is completed.
[0038] Step 1 in...