Box jacking method for performing correction on deflection end by virtue of jack in oblique crossing jacking process
A jacking and box technology, applied in the erection/assembly of bridges, bridges, buildings, etc., can solve the problems of uneven soil eating on both sides of the box, damage to the finished box, and deflection of the center line of the box. The effect of deviation correction is obvious, the construction speed is improved, and the operation is convenient.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0018] The box jacking method provided by the present invention, which uses jack picks to correct deviation at the deflection end during the oblique jacking process, will be described in detail below with reference to the accompanying drawings and specific embodiments.
[0019] Such as figure 1 — Figure 7 As shown, in the oblique jacking process provided by the present invention, the box jacking method using a jack pick to correct the deflection end includes the following steps in order:
[0020] 1) The existing railway at the jacking place shall be reinforced according to commonly used reinforcement methods;
[0021] 2) In the jacking area on both sides of the existing railway 6, a row of protective piles 2 is respectively arranged in the foundation soil on both sides of the box body 1 to be jacked along the jacking route, and two adjacent protective piles 2 are arranged alternately , and then set a zigzag crown beam 3 on the top of each row of protective piles 2, thereby ...