Construction method for continuous wall of crossing deep-buried large-sized municipal pipeline
A construction method and municipal technology, applied in sheet pile wall, infrastructure engineering, construction and other directions, can solve the problems of conflict between the enclosure structure and the existing pipeline, unable to complete the groove, mud loss, etc., to achieve strong construction operability, Duration saving, cost and duration reduction effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0020] This embodiment is a method for constructing a diaphragm wall across a large deep-buried municipal pipeline, so as to avoid the problem that a large amount of mud used for the retaining wall of the diaphragm wall will be lost from the pipeline during the construction of the diaphragm wall, and the construction is convenient and the cost is low. The concrete construction method of this embodiment is as follows:
[0021] a. Find and close the front and rear gates of municipal pipeline 1 passing through section 2 of the diaphragm wall to be constructed before construction, and pump out the water in this section of municipal pipeline or keep the water in the pipeline in a non-flowing state;
[0022] b. Such as image 3 As shown, on both sides of the diaphragm wall 2 and directly above the municipal pipeline 1, a steel casing 3 is used to protect the wall, and the hole is drilled to the top of the municipal pipeline 1, and the steel casing 3 is overlapped with the municipa...