Unlock instant, AI-driven research and patent intelligence for your innovation.

Construction technology of elevation difference joints in steel truss floor deck construction

A technology of steel truss and construction technology, applied in the direction of floors, building components, buildings, etc., can solve the problem of not including inspection standards, and achieve the effect of improving construction quality, increasing joint stiffness, and shortening construction period

Active Publication Date: 2016-06-15
广东省第四建筑工程有限公司
View PDF4 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] However, the quality control points and inspection standards of the floor deck technology in the construction application process have not been included in the standard
On the other hand, many practical difficulties such as the problems encountered in the construction process of the floor deck, solutions and standardized construction still exist

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction technology of elevation difference joints in steel truss floor deck construction
  • Construction technology of elevation difference joints in steel truss floor deck construction
  • Construction technology of elevation difference joints in steel truss floor deck construction

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0029] The invention will be further described below with specific examples:

[0030] refer to Figure 1 to Figure 5 , the elevation difference node construction process of steel truss floor deck construction, the steel truss floor deck adopted includes steel bar truss 31 and galvanized plate 30 connected to its bottom, including the following construction steps.

[0031] 1) Prepare Z-shaped backing plate and additional steel bars for nodes

[0032] According to the height difference H of the designed floor, a Z-shaped backing plate 2 is made in advance with a steel plate with a thickness of 5 mm. The Z-shaped backing plate 2 includes a vertical plate 20, and the two sides of the vertical plate 20 are vertically connected to the upper wing 21 and the lower wing 22 respectively. The width of the upper wing is 50mm, and the width of the lower wing is 60mm. The width of the riser 20 is equal to the height difference H of the design floor at the node; the additional reinforcement...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to the technical field of construction, and provides an elevation difference joint construction technology for steel bar truss floor deck construction. The elevation difference joint construction technology for steel bar truss floor deck construction comprises the steps of (1) preparing a Z-shaped bearing plate and joint additional bars; (2) installing the Z-shaped bearing plate and a side formwork, wherein the length of the portion, erected on a steel beam, of an upper portion of the Z-shaped bearing plate is at least 50mm; (3) installing a floor deck; (4) arranging the joint additional bars, wherein the two ends of each joint additional bar are welded to a steel bar truss of a high-elevation floor deck at the position of a change of the floor slab elevation and a steel bar truss of a low-elevation floor deck at the position of the change of the floor slab elevation respectively, and the middle section of each joint additional bar is arranged on a joint; (5) carrying out stud welding; (6) carrying out acceptance on a formwork installation project ; (7) carrying out concrete pouring. The elevation difference joint construction technology for steel bar truss floor deck construction has the remarkable and substantive advantages that due to the fact that the Z-shaped bearing plate and the additional bars are arranged at the position of the change of floor slab elevation, joint connection between elevation difference joints in the process of construction of the floor decks is achieved, construction quality of the high-and-low elevation difference joints of the floor decks is improved, the working procedure of construction is simplified, and the construction period is shortened.

Description

technical field [0001] The invention relates to the technical field of building construction, in particular to the construction technology of reinforced truss floor decks. Background technique [0002] Reinforced truss floor deck is a new building composite material highly recommended by the construction industry today. It has the advantages of light weight, high strength, factory production, convenient installation, beautiful and durable, etc. It is an advanced building decoration material integrating construction and decoration. [0003] In the field of design and construction of steel structure floor slabs, the National Standards Committee promulgated the national standard "Reinforced Truss Floor Slabs" on February 09, 2012, and it will be implemented on August 1, 2012. This standard specifies the terms and definitions, marks and examples, materials, requirements, test methods, inspection rules, ordering content, signs, packaging, transportation and storage of reinforced ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E04B5/40
Inventor 吐尔洪太·潘海尔丁罗耀海何汉林钟自强邓志凯周宇温志平林培东杨曲波张剑锋王佛来刘柳炼朱臣陈桅罗祥玮
Owner 广东省第四建筑工程有限公司