Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

A Method of Determining the Elevation of Drilled Cast-in-situ Pile Using Laser Line Meter

A technology of bored piles and laser liners, which can be used in sheet pile walls, foundation structure tests, construction, etc., can solve the problems of increasing professional investment, affecting construction progress, and wasting manpower, so as to avoid leveling errors , Improve construction efficiency and save construction cost

Active Publication Date: 2016-03-30
CHINA RAILWAY SIXTH GRP TIANJIN RAILWAY CONSTR +1
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Because it is impossible to bury the casing at each pile position at the same time, the casing can only be pulled out after one pile is drilled and then buried to the next pile. That is to say, an elevation measurement is required every time the casing is buried. This leads to an increase in the frequency of measurements, which is prone to measurement errors
[0005] (2) The amount of calculation is large and it is easy to cause errors
[0006] The measured data needs to be calculated one by one relative to ±0.000, so that the specific hole depth of each pile can be obtained, which will undoubtedly increase the calculation amount and cause calculation errors
[0007] (3) Use measuring rope to measure the drilling depth, which is a waste of manpower and has a large error
[0008] During the drilling process, someone must continuously measure the size from the bottom of the hole to the top surface of the casing with a measuring rope, so as to judge whether the design elevation of the bottom of the hole has been drilled, which is a waste of manpower and the measurement data is inaccurate
[0009] (4) Continuous construction day and night requires more surveyors
Each shift of measurement requires at least 3 professional surveyors for real-time control, including 1 person to measure the ruler, 1 person to observe, and 1 person to re-measure and record data. If calculated as 3 working days per day, 3 measurement teams with a total of 9 people are required can be completed, which will increase the investment of professionals
[0011] (5) The line of sight is affected at night, the supervisor cannot implement the acceptance procedure, and the site is stagnant
[0012] Due to the dim light during construction at night, accurate readings cannot be made through the leveling rod, and the conditions for leveling measurement are not available, which will easily lead to the loss of control of the height of the cast-in-situ pile
In addition, it is also difficult for the supervisory engineer at the side station to check and accept the depth of the hole, and it is likely to ask for re-inspection during the day, so that subsequent construction cannot be carried out, resulting in on-site delays and mechanical stagnation, affecting the construction progress

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A Method of Determining the Elevation of Drilled Cast-in-situ Pile Using Laser Line Meter
  • A Method of Determining the Elevation of Drilled Cast-in-situ Pile Using Laser Line Meter
  • A Method of Determining the Elevation of Drilled Cast-in-situ Pile Using Laser Line Meter

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0040] The method for determining the elevation of bored piles provided by the present invention using a laser line thrower will be described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0041] Such as figure 1 — image 3 As shown, the method for determining the elevation of bored piles provided by the present invention using a laser line instrument includes the following steps carried out in order:

[0042] 1) First, vertically set the elevation control pile 1 on the ground close to the construction range of the bored pile, and mark 2 on the elevation control pile 1 as the absolute elevation;

[0043] 2) Before drilling, the first section of drill pipe 4 with the drill bit 3 and the subsequent multi-section drill pipe 5 are sequentially connected to form the drill pipe 6 at the construction site, so that the length of the entire drill pipe 6 is longer than that of the borehole filling The sum of the hole bottom elevation of the p...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a method for determining the elevation of a bored pile through a cross line laser. The method includes the steps that an elevation control pile is arranged on the ground; marks are marked on a drill rod and a sliding staff; the cross line laser is used for controlling the elevation of the bottom of a drill hole and the elevation of the top of the bored pile. The method has the advantages that leveling work is not needed, and therefore efficiency is improved; data calculation is not needed, and therefore time is shortened; a measuring line does not need to be used for measuring the depth of the bottom of the hole, and therefore the number of employed measuring professionals is greatly decreased. A supervision acceptance procedure can be finished at night, and therefore construction is accelerated. In a word, according to the method, the elevation of the bored pile is easy, convenient and rapid to achieve effortlessly, labor is saved, the construction cost is reduced, the construction is accelerated, and construction efficiency is greatly improved.

Description

technical field [0001] The invention belongs to the technical field of civil construction, and in particular relates to a method for determining the elevation of bored piles by using a laser line thrower. Background technique [0002] In the traditional bored pile construction, the casing must be buried in advance at the hole, its function is to control the hole position of the bored pile; the second is to control the elevation of the bottom of the hole after drilling by measuring the elevation of the top surface of the casing. That is to control the drilling depth. Because the casing needs to be buried before each pile is driven in, and the elevation of the casing cannot be accurately controlled, so the top elevation of each casing of each pile is different, so it is necessary to measure the height of each pile casing The elevation of the top surface, and the depth of driving each pile relative to the top surface of the casing through calculation. However, this traditiona...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D5/36E02D33/00
Inventor 张磊马祥春薄海李亚林崔明尧霍琨陈丰锐熊英
Owner CHINA RAILWAY SIXTH GRP TIANJIN RAILWAY CONSTR
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products