Risk assessment method for construction period and cost of anti-seepage and water-proof curtain body
A water-stop curtain and risk assessment technology, applied in special data processing applications, instruments, electrical digital data processing, etc., can solve the problem of increased construction difficulty, difficult control of construction period and cost, and failure to meet the requirements of design scheme and construction organization design preparation and other problems to achieve the effect of reducing the risk of construction cost
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0034] The risk assessment method for the construction period and cost of the anti-seepage and water-proof curtain body proposed by the present invention will be further described in detail below in conjunction with specific examples. Advantages and features of the present invention will be apparent from the following description and claims.
[0035] This embodiment discloses a risk assessment method for the construction period and cost of an anti-seepage and water-proof curtain body, including steps:
[0036] Step 1. Analysis of the distribution of coral reef limestone: Site survey, according to the site survey report, count the probability of encountering coral reef limestone and the distribution probability of coral reef limestone thickness during drilling construction.
[0037] Site survey, according to the survey report of the proposed project site, make statistics according to the probability of encountering coral reef limestone during drilling construction. Probability...