[0014] In order to make the object, technical solution and advantages of the present invention more clear, the present invention will be further described in detail below in conjunction with the examples. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.
[0015] A high pier without support formwork construction process, including step A: formwork preparation; step B: formwork installation; step C: formwork inspection; step D: formwork derusting and oiling; step E: formwork climbing operation ; Step F: install formwork for each section; Step G: remove formwork, and construct to the top of the pier.
[0016] Step A: Formwork preparation. When determining the edge line of the formwork, refer to the center of the base top, and level the outside edge of the formwork. Level the leveling layer with a level to level the hanging lines. After the mortar hardens, the formwork needs to ...