Fixing Method of Anchor Static Pressure Pile Machine Base

A technology of static pressure pile driver and fixing method, which is applied in sheet pile wall, construction, infrastructure engineering, etc., can solve the problem that the pipe pile cannot be pressed in, the center and the center of the reserved hole of the pipe pile do not coincide, and the cost of materials and labor increases. and other problems, to achieve the effect of saving material and labor costs, reducing anchoring labor costs, and eliminating hidden safety hazards.

Active Publication Date: 2017-06-09
CHINA FIRST METALLURGICAL GROUP
View PDF6 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

At present, in the construction process of anchor static pressure pile pile machine base, two sets of anchor bars are usually pre-embedded in the concrete first, and the upper ends of the anchor bars protrude from the concrete surface, and then the body of the pile machine is installed on the two sets of anchor bars , and then press the pile. After the pile is completed, the exposed part needs to be cut off, and finally the head reinforcement is arranged to seal the pile head, but this will have the following problems: First, the anchor rod is pre-buried in the concrete alone, and the positioning accuracy is difficult to guarantee, resulting in two The center of the group anchor rod does not coincide with the center of the reserved hole of the pipe pile, so that the pipe pile cannot be pressed into the reserved hole of the pipe pile; secondly, the exposed part of the anchor rod affects the ground traffic and poses a safety hazard, and it is also easy to be hit by ground objects, resulting in The anchor itself and the upper end of the thread were severely damaged, making it impossible to install the pile driver; thirdly, the exposed part of the anchor had to be cut off after the pile was completed, resulting in an increase in material and labor costs; Adopt electric welding, increase cost

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Fixing Method of Anchor Static Pressure Pile Machine Base
  • Fixing Method of Anchor Static Pressure Pile Machine Base
  • Fixing Method of Anchor Static Pressure Pile Machine Base

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0030] In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.

[0031] Such as Figure 1-Figure 4 As shown, a method for fixing the base of an anchor static pressure pile pile machine comprises the following steps:

[0032] S1, such as Figure 1-Figure 3 As shown, a fixing device is made, which includes a steel plate 2, a plurality of anchors 8, a plurality of sleeves 7, and a plurality of anchor rods 11 configured with the plurality of sleeves 7, and a steel plate 2 is provided with a pipe pile The upper openings of the reserved holes 12 are reserved pile holes 10 of the same size, and a group of through holes 9 are respectively opened on the steel plate 2 o...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a fixing method for a base of a pile driver for a static-pressed pile by anchor rods. The fixing method includes the following steps that S1, a fixing device is manufactured, and the device comprises a steel plate, a plurality of anchors, a plurality of sleeves and the anchor rods matched with the sleeves; S2, before concrete pouring, the face, with the anchors, of the device is made to face downwards and is pre-embedded in the position above a pipe pile reserved hole, and then all through holes in the steel plate are sealed temporarily; S3, concrete is poured; S4, temporary sealing is removed completely, and the anchor rods are mounted in the sleeves; S5, the base of a pile driver body is mounted on the anchor rods through anchor rod holes in the base; S6, the driver body is mounted on the base, and pile pressing is carried out; S7, after pile pressing is completed, nuts are dismounted, and the anchor rods are recovered; and S8, end sealing ribs are distributed between the two sets of through holes. Through the fixing method, the positioning precision of the anchor rods can be ensured, the centers of the two sets of anchor rods are made to coincide with the centers of the pipe pile reserved hole, and it is ensured that a pipe pile is smoothly pressed into the pipe pile reserved hole.

Description

technical field [0001] The invention relates to an anchor static pressure pile, in particular to a method for fixing the base of an anchor static pressure pile machine. Background technique [0002] With the continuous development of the construction industry, the anchor static pressure pile is more and more used in high-rise buildings because of its simple structure, safety and reliability. At present, in the construction process of anchor static pressure pile pile machine base, two sets of anchor bars are usually pre-embedded in the concrete first, and the upper ends of the anchor bars protrude from the concrete surface, and then the body of the pile machine is installed on the two sets of anchor bars , and then press the pile. After the pile is completed, the exposed part needs to be cut off, and finally the head reinforcement is arranged to seal the pile head, but this will have the following problems: First, the anchor rod is pre-buried in the concrete alone, and the po...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D7/20
CPCE02D7/20E02D2600/30
Inventor 何红国李新革杨多娇杨旭
Owner CHINA FIRST METALLURGICAL GROUP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products