Construction method without chiseling pile head
A construction method and pile head technology, applied in sheet pile walls, infrastructure engineering, construction, etc., can solve the problems of waste of concrete and labor consumption, and achieve the effect of reducing construction cost, simplifying construction procedures, and improving construction safety.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0022] Refer to attached picture.
[0023] Exemption of the present invention removes pile head construction method and comprises the following steps:
[0024] Step 1, excavate the earthwork to the level of the bottom of the cap.
[0025] Before the hole is formed, the soil is excavated to the elevation of the bottom of the cap. In order to ensure the quality of the hole, avoid excessive hole drilling and avoid the disturbance of the pile body by the excavation after the pile is poured, the pile should be excavated before the hole is formed. The earthwork in the area will be excavated to the designed cap bottom elevation, and at the same time, a working surface will be provided for the inverted electric suspension rod in-situ stirring reinforcement method without chiseling pile heads.
[0026] Step 2, determine the concrete filling height of the pile body.
[0027] 2.1 Calculation of the rest elevation of the pile body concrete pouring: after the hole is formed, the pile bod...