Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Construction method of double arch tunnel auxiliary middle wall without middle pilot tunnel

A construction method, the technology of multi-arch tunnels, applied in tunnels, tunnel linings, earthwork drilling and mining, etc., can solve problems such as difficulty, inconvenient slag discharge, and complicated construction techniques, so as to improve construction efficiency, reduce construction period, and ensure construction safety Effect

Active Publication Date: 2017-05-31
HUNAN INSTITUTE OF ENGINEERING
View PDF5 Cites 12 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

At present, the common construction method is to construct the pilot tunnel first, and then construct the main tunnel. The construction process of this method is complicated, and the slag is inconvenient. The existence of the main tunnel will affect the excavation efficiency of the main tunnel; during the initial support construction process of the main tunnel, construction workers are prone to stepping into the air accident; at the same time, there are weak points in the connection between the support of the main tunnel and the middle wall of the pilot tunnel For example, in the construction of the initial branch of the main tunnel, the waterproof process of the connection point is complicated and difficult; if the vault of the intermediate pilot tunnel is not filled densely, it is easy to cause a large bias at the primary branch of the main tunnel, etc.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of double arch tunnel auxiliary middle wall without middle pilot tunnel
  • Construction method of double arch tunnel auxiliary middle wall without middle pilot tunnel
  • Construction method of double arch tunnel auxiliary middle wall without middle pilot tunnel

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0019] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments.

[0020] see Figure 1 to Figure 6 , the left tunnel 1 in the figure is the first tunnel, the right tunnel 2 is the rear tunnel, and the third is the auxiliary middle wall. The dimensions in the figure are in cm.

[0021] In this embodiment, the construction steps of the auxiliary middle wall of the multi-arch tunnel without the middle pilot tunnel are as follows:

[0022] Excavate the left tunnel 1 first, and the construction sequence of the left tunnel 1 is: first construct the upper step 4 (the upper step 4 is the area above 1.6 meters above the design datum line 5), adopt conventional construction methods; then construct the initial support 6 , note that in the position of the auxiliary middle wall 3 in the design, it is necessary to embed embedded parts on the initial support 6 to facilitate the connection in later construction; after the...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method of a double arch tunnel auxiliary middle wall without a middle pilot tunnel. According to the technical points, firstly, an upper step of a left side tunnel is constructed, then a primary support is constructed, and a lower step of the left side tunnel is excavated; the auxiliary middle wall is conducted, specifically, a vertical steel frame is constructed in the corresponding position of an inverted arch, after concrete of the inverted arch is constructed, an inclined strut on the right side of the steel frame is constructed, and a horizontal transverse-strut steel frame is constructed; rebars are fixed on the steel frame in a quincuncial mode; meanwhile, double layers of reinforcement fabrics are hung on the horizontal transverse-strut steel frame; then sprayed concrete is constructed on the steel frame, and a secondary lining of the left side tunnel is constructed on the left side of the concrete; and a right side tunnel is constructed, specifically, an upper step is excavated, then a primary support is constructed, a middle step is excavated, a primary support of the middle step is constructed, a lower step is excavated, the primary support and the inclined strut on the right side of the middle wall are dismantled, an inverted arch of the right side tunnel is constructed, and finally a secondary lining of the right side tunnel is constructed . Middle pilot tunnel construction is omitted, the construction safety of a main tunnel is guaranteed, an existing construction method is fully utilized, construction efficiency is improved, and the construction period is shortened.

Description

technical field [0001] The invention belongs to the construction method of a multi-arch tunnel in the field of tunnel engineering of civil engineering, and in particular relates to a construction method for an auxiliary middle wall of a multi-arch tunnel without a central pilot tunnel. Background technique [0002] In tunnel engineering, due to site and line constraints, multi-arch tunnels are often used (multi-arch tunnels refer to left and right parallel tunnels sharing a middle wall). At present, the common construction method is to construct the pilot tunnel first, and then construct the main tunnel. The construction process of this method is complicated, and the slag is inconvenient. The existence of the main tunnel will affect the excavation efficiency of the main tunnel; during the initial support construction process of the main tunnel, construction workers are prone to stepping into the air accident; at the same time, there are weak points in the connection between ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E21D11/10E21D9/00
CPCE21D9/00E21D11/107
Inventor 梁桥王军任振华刘杰段建周文权
Owner HUNAN INSTITUTE OF ENGINEERING
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products