A reinforcement construction method for channel-shaped slab platforms in operating subway stations
What is Al technical title?
Al technical title is built by PatSnap Al team. It summarizes the technical point description of the patent document.
A construction method and technology for subway stations, applied in construction, building maintenance, building construction, etc., can solve problems such as high safety risk and poor reinforcement effect, and achieve the goal of ensuring operational safety, improving worker work efficiency, and engineering quality control. Effect
Inactive Publication Date: 2019-11-05
ELECTROMECHANICAL DEVICE INSTALLATION OF CTCE GROUP
View PDF6 Cites 0 Cited by
Summary
Abstract
Description
Claims
Application Information
AI Technical Summary
This helps you quickly interpret patents by identifying the three key elements:
Problems solved by technology
Method used
Benefits of technology
Problems solved by technology
[0002] When the bearing capacity of the channeled slab platform of the operating subway station is not enough, it needs to be reinforced. The general reinforcement effect is not good, and the safety risk is high, and the channeled slab reinforcement construction of the operating subway station can only be carried out within three hours after the subway is out of service. , choosing convenient operation, ensuring the quality of reinforcement and the safety of the channel plate structure are the top priorities for channel plate reinforcement in operating subway stations. Reasonable selection of reinforcement technology is the key to ensuring project quality and operational safety. Therefore, how to choose how to strengthen the operation Ease of operation, guarantee of reinforcement quality, safety of channel plate structure and safety of subway operation are the issues that our engineers and technicians need to face
Method used
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more
Image
Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
Click on the blue label to locate the original text in one second.
Reading with bidirectional positioning of images and text.
Smart Image
Examples
Experimental program
Comparison scheme
Effect test
Embodiment Construction
[0028] Attached below figure 1 , attached figure 2 The present invention is described in detail:
[0029] refer to figure 1 , figure 2 , it includes 1 is the chemical anchor bolt; 2 is the angle steel bracket; 3 is the bottom steel formwork; 4 is the side steel formwork; 5 is the pouring trough; 6 is the high funnel; : hole taking; s4: reinforcement installation; s5: steel formwork installation; s6: cement-based grout mixing; s7: cement-based grout pouring and high-level funnel pressurization; s8: platform restoration; s9: point elimination, release line blockade ;
[0030] The specific implementation steps are as follows:
[0031] A construction method for reinforcing a channel-shaped plate platform of an operating subway station, the construction comprising the following steps:
[0032] s1: Please click to block the track line: please click in the operation dispatching room to block the track line in the designated area to ensure the safety of the operation line con...
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More
PUM
Login to View More
Abstract
The invention discloses a reinforcing construction method for a trough plate platform of an operation subway station and belongs to the technical field of reinforcing construction of operation subwaystation structures. The reinforcing construction method comprises the following steps of S1, construction applying and blockage of a track line, S2, construction preparation, S3, hole forming, S4, mounting of steel bars, S5, mounting of steel formworks, S6, stirring of cement foundation grouting materials, S7, pouring of the cement foundation grouting materials and pressurizing of a high funnel, S8, platform surface recovering and S9, applying of construction completion and removing of line blockage. According to the reinforcing construction method for the trough plate platform of the operation subway station, the two holes with the diameter being 90 mm are formed in a trough plate and serve as the pouring hole and the pressurizing hole correspondingly, and not only can the integrity of the overall structure of the trough plate platform and the safety of the operation station be guaranteed, but also the reinforcing construction requirements can be met; the assembled steel formworks areutilized as a part of the reinforcing structure, and convenience and rapidness are achieved; and the reinforcing construction method has the advantages that safety is high, operation is convenient, applicability is high, and manual operation strength is reduced.
Description
technical field [0001] The invention relates to a reinforcement construction method for a channel-shaped slab platform of an operating subway station, which is used for the structural reinforcement construction of an operating subway station, and is especially suitable for the reinforcement construction of a trough-shaped slab platform for an operating subway station, which can well meet the safety of the operating subway and the reinforcement of the station structure quality, belonging to the technical field of subway station structure reinforcement construction. Background technique [0002] When the bearing capacity of the channeled slab platform of the operating subway station is not enough, it needs to be reinforced. The general reinforcement effect is not good, and the safety risk is high, and the channeled slab reinforcement construction of the operating subway station can only be carried out within three hours after the subway is out of service. , choosing convenient...
Claims
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More
Application Information
Patent Timeline
Application Date:The date an application was filed.
Publication Date:The date a patent or application was officially published.
First Publication Date:The earliest publication date of a patent with the same application number.
Issue Date:Publication date of the patent grant document.
PCT Entry Date:The Entry date of PCT National Phase.
Estimated Expiry Date:The statutory expiry date of a patent right according to the Patent Law, and it is the longest term of protection that the patent right can achieve without the termination of the patent right due to other reasons(Term extension factor has been taken into account ).
Invalid Date:Actual expiry date is based on effective date or publication date of legal transaction data of invalid patent.
Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E04G23/02
CPCE04G23/02
Inventor 程维国曹远财陈秀花汪旺龙张涛孟志华向徽张志新
Owner ELECTROMECHANICAL DEVICE INSTALLATION OF CTCE GROUP