Construction method of bored pile in karst geological region
A construction method and technology of bored piles, applied in sheet pile walls, foundation structure engineering, construction, etc., can solve the problems of long construction period and high cost, and achieve the effects of simple construction, avoiding hole collapse, and reducing costs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Example Embodiment
[0020] Such as figure 1 As shown, this embodiment provides a method for constructing a bored pile in karst geology, which includes the following steps: Step S1: Drilling vertically downwards at a place to be drilled in karst geology, and determining whether there is a karst cave during drilling, If it exists, go to step S2, otherwise go to step S3; step S2: determine the position of the cave with respect to the pile foundation, if the cave is within the range set by the pile tip, first use concrete to fill the cave When the concrete is higher than the pile diameter of the cave roof and the concrete surface no longer drops, stop pouring. After the concrete reaches the set strength, continue to drill to the design pile bottom, and the final hole depth is in accordance with the cave The pile diameter below the bottom plate is not less than the set multiple. If the cave is not within the range set by the pile tip, the method of backfilling the clay and drilling the wall is adopted;...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap