Construction method of bored pile in karst geological region
A construction method and technology of bored piles, applied in sheet pile walls, foundation structure engineering, construction, etc., can solve the problems of long construction period and high cost, and achieve the effects of simple construction, avoiding hole collapse, and reducing costs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0020] Such as figure 1 As shown, the present embodiment provides a construction method for karst geological bored piles, including the following steps: Step S1: Drilling vertically downward at the place to be drilled in karst geology, and judging whether there is a karst cave during drilling, If it exists, go to step S2, otherwise go to step S3; step S2: judge the position of the karst cave relative to the pile foundation, if the karst cave is within the range set by the pile tip, first fill the karst cave with concrete until the concrete is higher than the pile diameter height of the roof of the karst cave and the concrete surface no longer drops, stop pouring. After the concrete reaches the set strength, continue drilling into the hole to the bottom of the designed pile, and the depth of the final hole is in accordance with the karst cave. The pile diameter below the bottom plate is not less than the set multiple; if the karst cave is not within the range set by the pile ti...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com