Construction method for building girder bridge across business line

A construction method and technology for business lines, which are applied in the construction field of building beam bridges across business lines, can solve the problems of high traffic density of railway lines, impact on railway operation safety, and difficulty in construction, so as to save costs, reduce the number of construction blockades, Improve the effect of construction safety

Active Publication Date: 2018-06-15
CTCE GRP ROAD & BRIDGE ENG CO LTD
View PDF5 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] Due to the high traffic density and heavy traffic on the railway line, the construction near and across the railway line will have a great impact on the safety of railway operation, and at the same time, the construction is difficult due to the impact of the business line

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0024] The technical solutions in the embodiments of the present invention are clearly and completely described below. Obviously, the described embodiments are only some embodiments of the present invention, rather than all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

[0025] The invention provides a construction method for building a girder bridge across the business line, comprising the following steps:

[0026] Two rows of steel sheet piles are respectively installed at 3.7m on both sides of the down line of the business line. The anchorage depth of the steel sheet piles is greater than the predetermined value, which is determined according to the characteristics of this project; adjacent occlusion; in a specific construction project, the predetermined value is 4.69m,

[0027] Backfilling and com...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method for a building girder bridge across a business line. The construction method comprises the following steps that two rows of steel sheet piles are separately driven at the positions being 3.7m from both sides of an upstream and downstream lines of the business line, and the anchorage depth of steel sheet piles is greater than a predetermined value; adjacent steel sheet pile are interlocked; first layers of concrete of a bearing platform and side walls are poured; the positions of steel sheet piles are backfilled and compacted when the steel sheet piles are removed; steel pipes are driven to be grouted and multiple holes are formed in the steel pipes; connection protection of steel pipe columns is arranged, the bottom is reinforced concrete foundation, and the spacing of the steel pipe and columns is 4.2m, the steel pipe columns are connected by channel steel, and wire mesh is arranged between the steel pipe columns; wall body formworks of the side walls adopt steel and wood composite formworks, and the concrete of the side walls is poured three times; cover plate beams are erected by a crane, an overhead bridge is installed by adopting aseparable combination mode; and a temporary traffic crossing is arranged. According to the construction method for the building girder bridge across the business line, the amount of construction blockade of the business line is reduced, the construction period is shortened, and the cost is saved.

Description

technical field [0001] The invention relates to a construction method for constructing a girder bridge across a business line. Background technique [0002] The cover slab girder bridge of the railway comprehensive freight yard project needs to be built across the railway line. [0003] Due to the high traffic density and heavy traffic on the railway line, the construction near and across the railway line will have a great impact on the safety of railway operation, and the construction is difficult due to the impact of the business line. Therefore, under the condition of ensuring the safe operation of the commercial line railway, minimizing the impact on the operation of the commercial line, speeding up the construction progress, and reducing the cost expenditure are technical problems that need to be solved urgently. Contents of the invention [0004] The invention proposes a construction method for building a girder bridge across the business line. During the constructi...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E01D21/00E02D27/12
CPCE01D21/00E02D27/12
Inventor 杨玉龙刘前来李春风孙顾伟韩利彪郁有好马财亮王明亮
Owner CTCE GRP ROAD & BRIDGE ENG CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Eureka Blog
Learn More
PatSnap group products