Construction method for crossing of shield through sand and gravel backfill area

A construction method and a technology of sand and gravel materials, which are applied in the direction of earthwork drilling, mining equipment, tunnels, etc., can solve problems that have not been studied in depth in construction, reduce the number of tool changes when opening warehouses, ensure the safety of buildings and structures, and avoid serious wear and tear Effect

Active Publication Date: 2018-06-29
SHANGHAI TUNNEL ENG CO LTD +1
View PDF7 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, there is no domestic subway tunnel construction in the sand and gravel backfill area, and there is no in-depth research on the construction of shield tunneling through the sand and gravel backfill area.
[0004] However, it is a very complicated problem for shield tunneling through the sand and gravel backfill area, and there are very few related researches in China at present, and there are many topics worthy of research, such as reasonable soil reinforcement methods, shield cutter head selection, shield parameter control, etc. These are subject to further research

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for crossing of shield through sand and gravel backfill area
  • Construction method for crossing of shield through sand and gravel backfill area
  • Construction method for crossing of shield through sand and gravel backfill area

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0031] Embodiments of the present invention are described below through specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the content disclosed in this specification. The present invention can also be implemented or applied through other different specific implementation modes, and various modifications or changes can be made to the details in this specification based on different viewpoints and applications without departing from the spirit of the present invention.

[0032] At present, conventional soil reinforcement and shield tunneling technology are widely used, but the sand and gravel backfill area has complex strata, uneven soil structure, and large differences in physical and mechanical properties. Conventional treatment methods cannot adapt to the advancement of earth pressure balance shield tunneling. , cannot be changed in real time to meet actual needs.

[0033] For the sand and gravel b...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a construction method for crossing of a shield through a sand and gravel backfill area. The construction method comprises the steps that before the shield crosses through the sand and gravel backfill area, through a sleeve valve pipe, reinforcing slurry with certain pressure is injected into the sand and gravel backfill area needing to be reinforced; when the shield conducts tunneling to be away from the sand and gravel backfill area by a certain distance, a shield cutterhead is overhauled, and it is ensured that the shield cutterhead enters the sand and gravel backfillarea in an intact state; the shield tries to conduct tunneling into the sand and gravel backfill area by a section of distance, tunneling parameters and change of the sand and gravel backfill area inthe tunneling trying process are monitored, and the tunneling parameters and modes suitable for the sand and gravel backfill area are obtained; and the shield crosses through the sand and gravel backfill area according to the obtained tunneling parameters and modes. According to the construction method, the filling effect of loess cement paste slurry in a loose peddle layer is good, clay cement slurry with sample cores visible partially wraps peddle, consolidation is good, certain strength is achieved, in the shield propelling process, the soil pressure can be built, and shield propelling safety is ensured.

Description

technical field [0001] The invention relates to the technical field of crossing construction of subway tunnels, in particular to a construction method for shield tunneling through sand and gravel backfill areas. Background technique [0002] With the continuous development of subway projects across the country, shield construction technology has been more and more widely used. In the construction of urban subway tunnels using the shield method, it is inevitable to have a certain degree of impact on the ground buildings (structures) along the line. During shield construction, it is necessary to ensure the safety of the construction tunnel itself and solve the problem of shielding. The impact on the adjacent existing buildings (structures) when the structure passes through the stratum. Especially when the subway tunnel adopts the earth pressure shield construction technology to pass through the special stratum in the sand and pebble backfill area, due to the complex compositi...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E21D9/08E21D9/093E21D9/00
CPCE21D9/001E21D9/08E21D9/093
Inventor 李万林卓发成黄德中李刚张亮施军顾蓓炯冯玉权曹红寇晓勇
Owner SHANGHAI TUNNEL ENG CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products