Construction method of temporary shortcut of construction site
A technology of construction site and construction method, which is applied in the construction field of temporary roads, can solve the problems of ineffective utilization of construction waste and spoil, and achieve the effect of satisfying road deformation requirements, realizing recycling and reuse, and increasing deformation stability.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0014] In order to further understand the invention content, characteristics and effects of the present invention, the following examples are given, and detailed descriptions are as follows in conjunction with the accompanying drawings:
[0015] see figure 1 , a construction method for a temporary access road at a construction site, the following steps are adopted:
[0016] 1) According to the strength requirements and use requirements of the temporary access road, mix waste soil, construction waste, cement and water together, and conduct a trial mix test of the mixing ratio, and at the same time make the cement firmly bond the waste soil and construction waste together,
[0017] 2) According to the mixing ratio determined in step 1), mix the waste soil, construction waste, cement and water evenly;
[0018] 3) The mixture of waste soil, construction waste, cement and water mixed uniformly in step 2) is paved and rolled in layers to form the roadbed 1;
[0019] 4) steel mesh ...