Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

A suspension installation method for steel foundation of tower crane

The technology of a tower crane and an installation method, which is applied in the direction of cranes and the like, can solve the problems such as the inability to complete the lifting tools, the inability to guarantee the construction period, and the waste of manpower and material resources, and achieve the effects of novel design, low cost, and high environmental protection efficiency.

Active Publication Date: 2019-07-16
THE SECOND CONSTR ENG CO LTD CCSEB
View PDF6 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] In the mid-to-late stage of high-rise building construction, a batch of structural parts with a single weight of 16t need to be hoisted to a height of 220m above the ground for use. This height cannot be hoisted by truck cranes. Tower cranes can meet the performance requirements. The lifting weight of a single piece is 16t and the lifting height is 300m. However, the conventional concrete foundation was not considered in the early stage. It is impossible to excavate a large area on the ground around the high-rise building to make a conventional concrete foundation. Using the existing steel strands for hoisting is too slow. Waste of manpower and material resources, the construction period cannot be guaranteed, and other lifting tools cannot be completed

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A suspension installation method for steel foundation of tower crane
  • A suspension installation method for steel foundation of tower crane
  • A suspension installation method for steel foundation of tower crane

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0021] Such as Figure 1-Figure 5 Shown, a kind of tower crane steel foundation suspension installation method of the present invention comprises the following steps:

[0022] (1) Process the steel foundation 1 according to the distance between two adjacent structural columns on the outside of the building, that is, the cross-sectional size of the structural columns;

[0023] (2) At a suitable height, install the steel foundation 1 between two adjacent structural columns and extend to the outside of the building;

[0024] (3) Weld the foot 3 of the tower crane 2 to the steel foundation 1 after setting out and positioning on the steel foundation 1;

[0025] (4) According to the installation instructions of the tower crane 2 manual, install the foundation section, the bracket, the slewing assembly, the slewing tower body section, the tower top bracket assembly, the balance arm, the lifting arm until the tower crane 2 is completely installed.

[0026] According to the maximum w...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a tower crane steel foundation suspension installing method. The tower crane steel foundation suspension installing method comprises the following steps that (1) a steel foundation is machined according to the distance between two adjacent structure columns on the outer side of a building, namely the size of the cross section of the structure columns; (2) at the appropriate height, the steel foundation is installed between the two adjacent structure columns and extends to the outer side of the building; (3) after unwinding positioning on the steel foundation, machine legs of a tower crane are welded to the steel foundation; and (4) according to installation instructions of specifications of the tower crane, foundation joints, sleeve supports, rotary assemblies, slewing tower joints, tower top supporting frame assemblies, balance arms, cargo booms and the tower crane are totally installed in sequence. The tower crane steel foundation suspension installing methodis simple, quick, low in cost, short in time, saving in energy and high in environmental protection efficiency; meanwhile, the using manner of the tower crane is expanded, the very high practicability is achieved, and the good method is worthy of popularization.

Description

technical field [0001] The invention belongs to the technical field of building construction machinery and equipment, and in particular relates to a suspension installation method for a steel foundation of a tower crane. Background technique [0002] In the mid-to-late stage of high-rise building construction, a batch of structural parts with a single weight of 16t need to be hoisted to a height of 220m above the ground for use. This height cannot be hoisted by truck cranes. Tower cranes can meet the performance requirements. The lifting weight of a single piece is 16t and the lifting height is 300m. However, the conventional concrete foundation was not considered in the early stage. It is impossible to excavate a large area on the ground around the high-rise building to make a conventional concrete foundation. Using the existing steel strands for hoisting is too slow. Manpower and material resources are wasted, and the construction period cannot be guaranteed, and other lif...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): B66C23/20B66C23/28B66C23/62
CPCB66C23/20B66C23/283B66C23/62
Inventor 崔文才闫许锋范吉英高东宇
Owner THE SECOND CONSTR ENG CO LTD CCSEB
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products