Steel pipe pile anti-freezing cracking method suitable for bridge water construction in frozen area
A technology for steel pipe piles and anti-freeze cracking, which is applied to sheet pile walls, infrastructure engineering, protection devices, etc. problems, to ensure the stability of the structure, to avoid brittle failure and freeze cracking.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0012] A method for preventing freezing and cracking of steel pipe piles suitable for construction of bridges in frozen regions provided by the present invention is as follows:
[0013] Such as figure 1 , figure 2 As shown, an upper limit collar 2 is welded on the inner wall of the steel pipe pile 1, and a limit collar 3 is welded at a certain height below the upper limit collar 2 on the inner wall of the steel pipe pile. The upper limit collar 2 and the lower limit collar 3 It is a circular ring made of steel bars or steel plate rings. The outer side of the ring is welded to the inner wall of the steel pipe pile, and the inner side is evenly welded with 4 equal-length limit rods 4 opposite to the center of the steel pipe pile. There is a certain distance between the front ends of the limit rod 4;
[0014] Insert and drive the lower end of the steel pipe pile at the design depth of the water bottom to maintain a certain water level inside the steel pipe pile;
[0015] A fl...