A suspension bridge and construction method technology, applied in suspension bridges, bridge construction, bridges, etc., can solve the problems of increasing the balance weight, unable to push the cable saddle, unfavorable side span hoisting, etc., to reduce the bending moment and the force of the bridge tower. safe effect
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2018-10-12
Smart Images

Figure 1 
Figure 2
Abstract
Description
technical field
[0001] The invention belongs to the technical field of bridge construction, and in particular relates to a temporary anchor cable balancing construction method in the erection process of a main girder of a suspension bridge. Background technique
[0002] In the construction of existing suspension bridges, the mid-span and side-span are often used to alternately hoist the main girder segments combined with the construction method of saddle jacking. When the unbalanced force generated by the main When the value is high, the unbalanced force is released by pushing the saddle to reduce the bending moment of the tower.
[0003] With the advancement of construction technology and the development of hoisting equipment, the weight of a single beam segment is increasing. According to the traditional construction method, when the beam section is hoisted at the mid-span, because the weight of a single beam section is too large, the increase in the main cable force of t...
Examples
Embodiment Construction
[0015] The specific embodiments of the present invention will be described in detail below in conjunction with the technical solutions and accompanying drawings.
[0016] A main span 400m, the ground-anchored suspension bridge of side span 150m, the weight of each girder section is 600 tons, adopts the method of the present invention to implement as follows:
[0017] 1) The main beam 5 of the first section of the side span near the anchorage 1 is first installed on the bracket 4, and the temporary anchor cable 2 is installed, and the bracket 4 at the anchorage 1 on the other side and the second side span of the side span are symmetrically constructed. One section of the main beam 5, and install the temporary anchor cable 2, the temporary anchor cable 2 only needs to be stretched straight, without tension;