Reinforcement structure and method of structures passing through large section tunnel group in soft soil rich in water
A technology for strengthening structures and large sections, applied in tunnels, earthwork drilling, tunnel lining, etc., can solve the problems of sand blasting and water inflow, affecting the structural safety and normal use function of structures, and excessive deformation of the initial support, achieving high safety. , The social and economic benefits are obvious, and the construction is convenient.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0031] The present invention will be described in detail below in combination with specific embodiments.
[0032] The reinforcement method for the underpass structure of the large-section tunnel group in soft soil rich in water includes the following steps:
[0033] Step 1: Set up an open-cut well 10 at the end outside a certain horizontal distance outside the structural sideline of the existing structure 1 above the tunnel. The open-cut well 10 at the end is used as the construction space for the horizontal reinforcement and protection measures of the later excavation tunnel and the excavation opening of the underground excavation tunnel Construction of the end cut well enclosure pile 7 (or the end open cut well enclosure wall) of the open cut section of the end well, the vertical stratum reinforcement flexible pile 3 and the inclined direction on both sides of the existing structure 1 above the tunnel are carried out simultaneously. The construction of grouting pipe 8;
[0...