Prefabricated thermal insulation double-layer bent pipe and its preparation method
A bending and double-layer technology, which is applied in the field of urban heating directly buried hot water pipeline engineering, can solve the problems of insufficient bending and deformation resistance of the bending pipe, and achieve the effects of long fatigue life, improved bearing capacity, and reduced maximum stress.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0026] Embodiment 1: The core pipe elbow 1 and the core pipe elbow straight pipe arm 2 constitute the core pipe; the casing pipe elbow 3 and the casing pipe elbow straight pipe arm 4 constitute the casing pipe.
[0027] figure 1 As shown, in this embodiment, there is 1 core tube elbow, 2 core tube elbow straight tube arms, 4 connecting plates, 1 casing elbow, 2 casing elbow straight tube arms, and 2 annular plugs .
[0028] The production process of this embodiment: first, the core pipe elbow 1 and the core pipe elbow straight pipe arm 2 are welded into a core pipe, and the angle β of the core pipe elbow is 90 degrees; secondly, the core pipe and the connecting plate 5 are connected under normal or preheating conditions Welding; then both sides of the core pipe wear annular plugs 6, and under normal or preheating conditions, the annular plugs 6 are welded to the core pipe 2, and the annular plugs 6 are welded to the connecting plate 5; next, the casing elbows 3 and Casing el...
Embodiment 2
[0030] Embodiment 2: In this embodiment, there is 1 core tube, 1 sleeve pipe, 4 connecting plates, and 2 annular plugs.
[0031] The production process of this embodiment: firstly, the integrated core tube 9 is made, and the angle β of the core tube elbow is 85 degrees; secondly, the welding of the four connecting plates 5 and the core tube 9 is completed under the normal or preheating state; then the core tube 9 is two The side piercing ring plug 6 is welded to the core tube 2 under normal or preheating conditions, and the ring plug 6 is welded to the connecting plate 5; next, the integrated casing 10 is made, and the casing 10 is installed. Under normal or preheating conditions, the casing 10 is welded to the annular plug 6 . Finally, an insulation layer 7 is added to the outer surface of the casing; a protective layer 8 is added to the outer surface of the insulation layer 7 .
Embodiment 3
[0032] Embodiment 3: The angle β of the elbow of the core tube of the present invention is 100 degrees, and other contents are the same as in Embodiment 1.