Suspension Structure and Construction Method of Adding Second Floor Slab on Super High Floor
A suspension structure and floor technology, applied in building construction, construction, building maintenance, etc., can solve the problems of reducing the usable area, destroying the integrity of the building, waste, etc. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0024] A suspension structure for adding a second-floor slab to a super high floor, comprising: a house, the house has a left wall 1 and a right wall 2 in the length direction, and the left wall has a group of parallel walls. The left socket 3, the right wall has a set of right sockets 4 parallel to each other, a cross joist 5 is inserted between the left socket and the right socket, and the left side of the cross joist is opened There is a left first port 6 and a left second port 7, the left first port and the left second port are connected to the left lifting assembly, and the left lifting assembly is fixed on the On the left wall, the right side of the cross joist is provided with a right first port 9 and a right second port 10, and the right first port and the right second port are connected to the right hoisting assembly. The right hoisting assembly is fixed on the right wall through a set of expansion bolts.
[0025] The left socket and the right socket not only play th...
Embodiment 2
[0027] In the suspension structure of adding a second-floor slab to a super high floor described in Embodiment 1, the left suspension assembly includes a left suspension plate 11, and the left suspension plate is attached to the left wall and is expanded by The bolts are fixed, the bottom of the left hanging plate is inserted into the left opening, the left hanging plate is vertically fixedly connected to the left supporting plate 12, and the left supporting plate is vertically fixedly connected to the left inserting plate 13, and the The left inserting plate is vertically fixedly connected to the left elastic fixing plate 14, and the right side of the left two-way port is connected to the left horizontal groove 15, and the left inserting plate is inserted into the left two-way opening, and the left elastic fixing plate Insert it into the left lying groove and fix it with screws. The left supporting plate is attached to the bottom between the left first port and the left second...
Embodiment 3
[0030] In the suspension structure of adding a second-floor slab to a super-high floor described in Embodiment 1, the right suspension assembly includes a right suspension plate 16, and the right suspension plate is attached to the right wall and is expanded by expansion. The bolts are fixed, the bottom of the right hanging plate is inserted into the first opening on the right, the right hanging plate is vertically and fixedly connected to the right supporting plate 17, and the described right supporting plate is vertically and fixedly connected to the right inserting plate 18. The right inserting plate is vertically fixedly connected to the right elastic fixing plate 19, the left side of the said right two-way port is connected to the right lying groove 20, the said right inserting plate is inserted into the said right two-way opening, and the said right elastic fixing plate Insert it into the right lying groove and fix it with screws. The right supporting plate is attached to...