Connecting and constructing method of prefabricated spliced bridge pier

A technology for prefabricating and assembling bridge piers, which is used in the erection/assembly of bridges, bridges, bridge parts, etc., can solve the problems of reduced seismic performance of bridge piers, and is not suitable for applications in high-intensity areas, and achieves improvement of shear resistance, reduction of steel bar tension and reduction. Possibility of concrete crushing, effect of enhancing bearing capacity

Active Publication Date: 2019-03-12
中恒宏瑞建设集团有限公司 +4
View PDF6 Cites 6 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Insufficient bearing capacity of the joints will directly lead to the reduction of the seismic performance of the bridge piers, making the prefabricated bridge piers with grouting sleeves connected to the steel bars not suitable for application in high-intensity areas

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Connecting and constructing method of prefabricated spliced bridge pier
  • Connecting and constructing method of prefabricated spliced bridge pier
  • Connecting and constructing method of prefabricated spliced bridge pier

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0032] In the following description, numerous specific details are given in order to provide a more thorough understanding of the present invention. It will be apparent, however, to one skilled in the art that the present invention may be practiced without one or more of these details. In other examples, some technical features known in the art are not described in order to avoid confusion with the present invention.

[0033] In order to thoroughly understand the present invention, detailed steps and detailed structures will be provided in the following description, so as to illustrate the technical solution of the present invention. Preferred embodiments of the present invention are described in detail below, however, the present invention may have other embodiments besides these detailed descriptions.

[0034] The invention provides a prefabricated assembled bridge pier connection structure and construction method using a grouting sleeve to connect steel bars. refer to F...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

PropertyMeasurementUnit
Thicknessaaaaaaaaaa
Login to View More

Abstract

The invention discloses a connecting and constructing method of a prefabricated spliced bridge pier. By increasing the length of one end of a grouting sleeve, the grouting sleeve goes deep into one side of a bridge pier section without the grouting sleeve, the grouting sleeve can penetrate through a seam, and therefore with the aid of the shearing resistance provided by a sleeve steel material, the shearing resistance of the whole seam is increased. Meanwhile, by means of the penetrating sleeve, the rigidity of the positions, near the two sides of the seam, of the bridge pier is increased, thebending resistance of the positions, near the two sides of the seam, of the bridge pier is enhanced, and the probability of rebar snapping and concrete crushing is reduced. Compared with the prior art, the method has the outstanding advantages that the damage of the bridge pier under the earthquake effect does not happen to joints any more by enhancing the bearing capacity of the joints, and themethod is better applied to the connection of the prefabricated spliced bridge pier and is particularly suitable for high-intensity areas.

Description

technical field [0001] The invention relates to a prefabricated assembled bridge pier connection structure and construction method using grouting sleeves to connect steel bars, which belongs to the technical field of prefabricated assembled structure engineering construction, and is especially suitable for high-intensity areas. Background technique [0002] Prefabricated segmental assembly construction technology has the advantages of less traffic interference, high construction quality, short construction period, low noise, and high construction safety, and has been more and more widely used in bridge construction, especially in busy cities and limited construction platforms at sea As well as the harsh natural construction, it has obvious advantages over the traditional cast-in-place construction technology. [0003] Prefabricated assembled bridge piers have been used in a large number of projects in Europe, America and other countries. The connection structure between comp...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E01D19/02E01D21/00
CPCE01D19/02E01D21/00
Inventor 李晓鹏焦峪波许坤韩强杜修力
Owner 中恒宏瑞建设集团有限公司
Features
  • R&D
  • Intellectual Property
  • Life Sciences
  • Materials
  • Tech Scout
Why Patsnap Eureka
  • Unparalleled Data Quality
  • Higher Quality Content
  • 60% Fewer Hallucinations
Social media
Patsnap Eureka Blog
Learn More