A construction method for overall hoisting after pre-bundling of steel bars for the roof of cast-in-place pipe gallery

A technology of overall hoisting and construction method, applied in artificial islands, water conservancy projects, infrastructure projects, etc., can solve the problems of limited storage area of ​​steel bars on site, neat stacking of difficult steel bars, affecting the civilized construction organization on site, etc.

Active Publication Date: 2021-03-26
CTCE GRP ROAD & BRIDGE ENG CO LTD +1
View PDF3 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

At present, most of the pipe gallery steel reinforcement projects still adopt the construction technology of on-site steel bar installation and forming, which greatly reduces the construction efficiency and the construction quality is difficult to guarantee. Especially, most of the pipe gallery construction is in the urban area, the construction work area is narrow, and the on-site steel bar storage area is limited. The stacking of steel bars on site has a great impact on the layout of the construction site and on-site traffic, and there are many steel bars stored on site, making it difficult to stack steel bars neatly and affect the civilized construction organization on site. Steel bars need to be transported repeatedly, which greatly affects construction efficiency

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A construction method for overall hoisting after pre-bundling of steel bars for the roof of cast-in-place pipe gallery
  • A construction method for overall hoisting after pre-bundling of steel bars for the roof of cast-in-place pipe gallery
  • A construction method for overall hoisting after pre-bundling of steel bars for the roof of cast-in-place pipe gallery

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0029] The present invention provides a construction method for overall hoisting after pre-binding steel bars for the roof of a cast-in-place pipe gallery. In order to make the purpose, technical solution and effect of the present invention clearer and more definite, the present invention will be further described in detail below. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.

[0030] The invention provides a construction method for overall hoisting after pre-binding of steel bars for the roof of cast-in-situ pipe gallery, which includes the following steps: it includes the steps of processing, assembling and positioning spot welding of the bent steel bars, fixing the steel bars on the hanger The steps of bending and transporting to the construction site, the steps of positioning and adjusting the steel frame and the overall hoisting, and the steps of positioning, adjustin...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses an overall hoisting construction method for pre-bundled steel bars for a cast-in-place pipe rack roof panel. The method comprises the following steps: processing, assembling and tack welding and connecting framed bent steel bars; fixing framed bent steel bars with a hanging bracket and transporting to a construction site; performing positioning adjustment on a framework ofthe steel bars, and performing overall hoisting; positioning, adjusting and decoupling the framework of the steel bars to complete the pre-binding. The steel bars are processed by numerical control equipment to ensure the processing precision of the steel bard, and the steel bars are pre-bundled through a steel bar positioner, so that the overall size of the framework of the steel bars is ensuredto be accurate; the overall hoisting of the steel bars is implemented by means of fine adjustment and other measures, so that the deviation of the site installation position of the steel bars is reduced, and the purpose of improving the installation quality of the main steel bars of a pipe rack is achieved; in the process of steel bars binding of a pipe rack roof panel, most of the main construction content is completed from a non-main line construction line, thereby saving the process time; the steel bar transportation, on-site storage and steel bar binding standardization are realized by theapplication of the steel bar hanging bracket of the pipe rack roof panel.

Description

technical field [0001] The invention relates to the field of construction of the roof of a pipe gallery, in particular to a construction method for overall hoisting after pre-binding of steel bars for the roof of a cast-in-place pipe gallery. Background technique [0002] At present, the urban underground comprehensive pipe corridor is one of the symbols of modernization, technology and intensification of urban construction. With the sustained and steady growth of my country's economy and the further acceleration of the urbanization process, the construction volume of underground comprehensive pipe corridors in my country has increased year by year. At present, most of the steel bar projects in the pipe gallery still adopt the construction technology of on-site steel bar installation and forming, which greatly reduces the construction efficiency and the construction quality is difficult to guarantee. Especially, most of the pipe gallery construction is in the urban area, the...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Patents(China)
IPC IPC(8): E02D29/045
CPCE02D29/10
Inventor 杨玉龙徐锋郁有好赵玉生蒲建国孙继禹郑胜赵光宇唐宝库王一农吴会强张丹宋兆龙孙洪龙
Owner CTCE GRP ROAD & BRIDGE ENG CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products