Construction method for out-of-terrace slurry retaining wall reinforced concrete cast-in-place pile
A technology of reinforced concrete and mud wall protection, applied in sheet pile wall, foundation structure engineering, construction and other directions, can solve the problems of low construction efficiency of soil excavation between piles, economic losses and safety hazards, unqualified pile head quality, etc. Reduce earthwork procedures, avoid disturbance or even damage, and improve the effect of construction progress
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0040] Such as Figure 1 to Figure 6 As shown, the construction method of the reinforced concrete cast-in-place pile with mud-out surface of the present invention includes the following steps:
[0041] Step 1. Leveling the foundation: Treat the foundation of the construction site. When the height of the original ground 14 of the construction site does not reach the design elevation of the floor, backfill the original ground 14 and backfill it to the elevation ground 13. Ground 13 is leveled to meet site design requirements;
[0042] When the height of the original ground 14 of the construction site is higher than the design elevation of the floor, the original ground 14 shall be excavated to the elevated ground 13, and the elevated ground 13 shall be leveled to meet the design requirements of the site;
[0043] It should be noted that the existing foundation leveling must reach the position above the steel sleeve of the present invention. When the height of the original ground 14 of...