Excavating construction method for surge shaft in gravel and sandy soil layer

A technology of gravel sand layer and construction method, which is applied in the field of surge well engineering, achieves the effects of high cost, difficult slag removal, and accelerated construction progress

Inactive Publication Date: 2016-06-29
SINOHYDRO BUREAU 11 CO LTD
View PDF4 Cites 5 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0014] Aiming at the above-mentioned problems existing in the prior art, the present invention proposes a construction method for excavating surge wells in gravel and

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Excavating construction method for surge shaft in gravel and sandy soil layer
  • Excavating construction method for surge shaft in gravel and sandy soil layer
  • Excavating construction method for surge shaft in gravel and sandy soil layer

Examples

Experimental program
Comparison scheme
Effect test

Example Embodiment

[0054] Attached below Figure 1~4 The examples and examples further illustrate the present invention.

[0055] In this embodiment, the method of the present invention is applied to the construction project of Shangma Xiangdi A Hydropower Station.

[0056] The surge tank of Shangmaxiangdi A Hydropower Station is arranged at the end of the water diversion system on the left bank of the Maxiangdi River. A circular section impedance surge tank with a diameter of 11.6m is excavated. The diameter of the impedance hole after lining is 3.2m and the diameter of the large well is 10m. The excavation height of the surge tank slope is about 50m, the top elevation of the well is EL938.10m, the bottom elevation of the impedance well is EL876.10m, and the height difference is 62m.

[0057] The surface of the surge tank is covered by collapsible gravel soil with a thickness of 15-25m; the bottom is bedrock with mica schist, mica quartz schist, and quartzite at the bottom; the bedrock is strongly we...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to an excavating construction method for a surge shaft in a gravel and sandy soil layer. The method comprises steps as follows: construction of rotary jet grouting combined cylinder piles, construction of raise-boring machine platform concrete, construction of a raise-boring machine as well as excavation and supporting of a sandy soil layer shaft body section. According to the method, high-pressure rotary jet grouting pile combined pile cylinders are used as raise-boring machine pilot shaft construction areas for the surge shaft in the gravel and sandy soil layer, annular steel arches are adopted for lower part layer-by-layer supporting under protection of a shaft top ring beam, excavation and deslagging are performed by the aid of a pilot shaft, vertical transport and hoisting equipment for excavating slag is not required to be mounted additionally, and the construction progress is greatly accelerated. For completion of excavation and supporting construction of the gravel and sandy soil layer with the depth being 15 m and the excavation diameter being 11.6 m, at least 60 days are required if the conventional drop shaft sinking method and the vertical excavation and wall protection method are adopted, the deslagging difficulty is very large, and the cost is very high; however, with the adoption of the method, the construction task can be completed within 42 days, and the grouting reinforcement effect of high-pressure rotary jet grouting piles in a colluvial gravel soil and rock block covering layer mainly comprising the gravel and sandy soil layer is good.

Description

technical field [0001] The invention relates to the field of surge well engineering, in particular to a construction method for excavating a surge well in gravel and sand layers. Background technique [0002] In the current field of surge well engineering, caisson method, direct stripping or vertical excavation method, and top-down retaining wall pouring excavation method are mainly used for excavation. The common point is that all slag materials are excavated through the top of the well. Dig transport. [0003] (1) caisson method [0004] Zhang Dengfeng published the paper "Application of caisson construction technology in the excavation of loose overburden of surge wells" published in the second issue of "Gansu Water Conservancy and Hydropower Technology" in 2010, introducing a caisson technology in surge wells with loose overburden For example, the side wall is supported by sinking while excavating, and the thickness of the retaining wall concrete varies from 0.5 to 1.5...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E02B9/06E02D17/06
CPCE02B9/06E02D17/06Y02E10/20
Inventor 陈雪湘杨士勇倪宏涛曹小杰李振波刘铁驹何文菊
Owner SINOHYDRO BUREAU 11 CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products