Construction method of fabricated composite wall house
A composite wall and construction method technology, applied to roofs, building roofs, roof coverings, etc., can solve problems such as insufficient construction speed, and achieve the effects of rapid construction, stable construction, and improved recycling rate
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0071] A lightweight composite wall, comprising a main wall layer 1, wall panels 2 are provided on both sides of the main wall layer 1; the main wall layer 1 includes a wall frame 11 and filled in the The wall core 12 within the wall frame 11. The wall frame 11 includes 112 , beam frame 111 and reinforcing rib 113 .
[0072] And the preparation method of this lightweight composite wall is:
[0073] Step 1: Place a layer of wall panels 2 horizontally on the tooling platform and position them;
[0074] Step 2: Paste one side of the wall frame 11 on the wall panel 2 with adhesive; the adhesive can be tile adhesive.
[0075] Step 3: Pour the mortar of the wall core material 12 into the wall frame 11; if an automatic operation is adopted, the volume in the wall frame 11 can be calculated, and the grouting amount and injection rate of the grouting equipment can be set. The amount of slurry requires that the wall body frame 11 is filled and spread out. When pouring the mortar of ...
Embodiment 2
[0084] A lightweight composite wall, comprising a main wall layer 1, wall panels 2 are provided on both sides of the main wall layer 1; the main wall layer 1 includes a wall frame 11 and filled in the The wall core 12 within the wall frame 11. A glass fiber mesh cloth 3 is arranged between the main wall layer 1 and the wall panel 2 .
[0085] And the preparation method of this lightweight composite wall is:
[0086] Step 1: Fix the template horizontally on the tooling platform;
[0087] Step 2: pouring the inorganic cementitious mortar into the formwork and flattening, initially forming the wall panel 2;
[0088] Step 3: laying glass fiber mesh cloth 3 on the wall panel 2 initially formed in the previous step;
[0089] Step 4: Put the wall frame 11 into the template, and press it on the glass fiber mesh cloth 3 in the previous step;
[0090] Step 5: Pour the mortar of the wall core material 12 into the wall frame 11 in the previous step; if automatic operation is adopted, ...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 