Construction Method of Underpass Pipe Gallery-Lining Door Opening Support
A construction method and doorway technology, applied in artificial islands, earthwork drilling, water conservancy projects, etc., can solve problems such as improper construction, economic losses, social and environmental impacts, and large investment in comprehensive pipe corridors, so as to ensure quality and shorten construction period , Reduce the effect of the process
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0040] The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.
[0041] see Figure 1-8 Shown, the present invention provides embodiment:
[0042] The construction method of the first-lined door opening support of the under-passing pipe gallery avoids the underground river 6, and includes the following construction steps:
[0043] S1. The surrounding structure of the working well adopts cast-in-place piles and double-pipe water-stop curtain occlusal support construction:
[0044] S11. In order to ensure the stability, bea...