A soil tunnel support structure crossing an existing railway and its construction method
A technology of support structure and construction method, applied in tunnels, earthwork drilling, tunnel lining and other directions, can solve the problems of slow construction progress, cumbersome procedures and low construction efficiency.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0063] see figure 1 , a support structure for an earth tunnel passing through an existing railway, comprising a starting shaft 1 and a receiving shaft 2, a supporting pipeline 15 is arranged between the starting shaft 1 and the receiving shaft 2, and the supporting pipeline 15 A positioning conduit 3 passes through the pipe section hole 12 reserved above; one end of the positioning conduit 3 is located in the starting well 1 , and the other end of the positioning conduit 3 is located in the receiving well 2 .
[0064] see figure 1 , a kind of soil tunnel support structure construction method that crosses existing railway, comprises the following steps:
[0065] Step 1: Preparatory work for construction, including:
[0066] 1.1. Select areas on both sides of the existing railway, and construct the originating shaft 1 and the receiving shaft 2;
[0067] 1.2. Set up several winches 5 on the well wall of the receiving shaft 2 away from the originating shaft 1, and set the drill...
Embodiment 2
[0108] see figure 1 , a support structure for an earth tunnel passing through an existing railway, comprising a starting shaft 1 and a receiving shaft 2, a supporting pipeline 15 is arranged between the starting shaft 1 and the receiving shaft 2, and the supporting pipeline 15 A positioning conduit 3 passes through the pipe section hole 12 reserved above; one end of the positioning conduit 3 is located in the starting well 1 , and the other end of the positioning conduit 3 is located in the receiving well 2 .
[0109] see figure 1 , a kind of soil tunnel support structure construction method that crosses existing railway, comprises the following steps:
[0110] Step 1: Preparatory work for construction, including:
[0111] 1.1. Select areas on both sides of the existing railway, and construct the originating shaft 1 and the receiving shaft 2;
[0112] 1.2. Set up several winches 5 on the well wall of the receiving shaft 2 away from the originating shaft 1, and set the drill...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com