A deep foundation pit dewatering construction method
A construction method and technology of deep foundation pits, which can be used in infrastructure engineering, construction, pump components, etc., and can solve problems such as inconvenient transportation and damage to pumps
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0042] Such as Figure 1 to Figure 5 Shown, a kind of deep foundation pit dewatering construction method of the present invention comprises the following steps:
[0043] 1) Connect the second steel pipe 12 of the suction pipe to the second positioning ring 16, then connect the cross bar 9 to the second positioning ring 16, connect the pre-embedded rod 14 to the cross bar 9 through threads, and connect the pre-embedded rod 14 fixed around the deep well 1;
[0044] 2) Adjust the position of the support plate 6 according to the diameter of the wellhead of the deep well 1, so that the support plate 6 is tightly pressed against the inner wall of the wellhead;
[0045] 3) Put the water pump 2 into the deep well 1, when the water pump 2 is put into the deep well 1, the anti-collision block 4 protects the water pump 2;
[0046] 4) Connect the horizontal plate 13 to the pre-embedded rod 14 through the fixing ring 8, and connect the second steel pipe 12 of the suction pipe to the first ...
Embodiment 2
[0053] On the basis of Embodiment 1, the cross section of the support plate 6 is an arc structure.
Embodiment 3
[0055] On the basis of Embodiment 1, the pumping pipe includes a first steel pipe 7, a flexible pipe 5 and a second steel pipe 12, and the two ends of the flexible pipe 5 are respectively connected with the first steel pipe 7 and the second steel pipe 12, and the buffer 3 is located on the outer wall of the first steel pipe 7, and the second steel pipe 12 is located in the second positioning ring 16. The outer wall of the second positioning ring 16 is also provided with two second fixing rods 18, the second fixing rods 18 are located on both sides of the axis of the second positioning ring 16, and the second fixing rods 18 are located below the cross bar 9 , the crossbar 9 is horizontally connected to the second positioning ring 16 through threads, and the second fixing rod 18 can fix the second steel pipe 12 in the second positioning ring 16 .
PUM