Construction method of prefabricated double-pipe seepage and drainage blind ditch and subgrade seepage and drainage structure

A seepage and drainage assembly-type technology, applied to drainage structures, side ditches/curbs, water/sewage treatment, etc., can solve problems such as poor drainage capacity, short service life, slow construction speed of roadbed seepage and drainage structures, etc., and achieve drainage Good ability and long service life

Active Publication Date: 2021-05-11
CHENGDU UNIVERSITY OF TECHNOLOGY
View PDF6 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] The first object of the present invention is to provide a prefabricated double-pipe drainage blind ditch to solve the technical problems of poor drainage capacity, short service life and slow construction in the blind ditch in the prior art
[0006] The second object of the present invention is to provide a construction method for roadbed seepage and drainage structure, so as to solve the technical problem of slow construction speed of roadbed seepage and drainage structure in the prior art
[0007] The third purpose of the present invention is to provide a roadbed seepage and drainage structure to solve the technical problems of poor drainage capacity, short service life and slow construction in the roadbed seepage and drainage structure in the prior art

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of prefabricated double-pipe seepage and drainage blind ditch and subgrade seepage and drainage structure
  • Construction method of prefabricated double-pipe seepage and drainage blind ditch and subgrade seepage and drainage structure
  • Construction method of prefabricated double-pipe seepage and drainage blind ditch and subgrade seepage and drainage structure

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0084]The assembled dual-tube seepage drain blind groove of the present embodiment includes a drain unit of the first tail connection, such asfigure 1 As shown, the drain unit includes a first pipe 100, a first filter layer 310, a second pipe 200, a second filter layer 320, and a support assembly 400, and a tube wall of the first pipe 100. An oil hole 110, the first filter layer 310 is wrapped in the outside of the first water pipe 100, and the second pipe 200 is disposed inside the first exhaust pipe 100, the second pipe 200 A second water infiltrating hole 210 is provided on the tube wall, the second filter layer 320 is wrapped in the outer portion of the second pipe 200 and forms a cavity between the inner wall of the first pipe 100 and the second filter layer 320. The first liquid obtained by filtration through the first filter layer 310 passes through the first water infiltrating hole 110 into the cavity, and the first clef is filtered by the second filter layer 320. The liquid...

Embodiment 2

[0093]Such asFigure 10 The subgrade seepage structure shown, including:

[0094]The blind groove 20, the blind groove 20 is an assembled dual tube blind groove of Example 1 or Example 2, and the blind groove 20 is mounted to the bottom of the trench 10;

[0095]The first return layer 30, the first return layer 30 is located around the blind groove 20 and the backfilling height is 15 cm above the height of the blind groove 20;

[0096]The third filter layer 40, the third filter layer 40 is located around the first return layer 30;

[0097]The second fill layer 50 is located above the first return layer 30 and the backfilling height matches the trench 10.

[0098]The construction method of the base seepage drainage structure includes the following steps:

[0099](1) The drainage unit of assembled double-tube seepaged drain blind groove is assembled;

[0100](2) Install the third filter layer 40 at the bottom and around the groove 10;

[0101](3) Place the drain unit into the trench 10 and connect the adjacen...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method of an assembled double-pipe seepage and drainage blind ditch and a subgrade seepage and drainage structure. The prefabricated double-pipe seepage drainage blind ditch includes a drainage unit connected end to end, and the drainage unit includes: a first drainage pipe, a first water seepage hole is provided on the pipe wall of the first drainage pipe; a first filter layer, the The first filter layer is wrapped on the outside of the first drainage pipe; the second drainage pipe is arranged inside the first drainage pipe, and the pipe wall of the second drainage pipe is provided with the second seepage hole; the second filter layer, the second filter layer wraps the outside of the second drain pipe and forms a cavity between the inner wall of the first drain pipe and the second filter layer. The invention has a simple structure, can be assembled in advance in the factory and then transported to the site, realizing the concept of assembly of all components, faster assembly speed and higher efficiency, less labor required for assembly, shorter assembly construction period, and lower construction cost and quality is easier to control.

Description

Technical field[0001]The present invention relates to the technical field of road seepage water, and in particular, it relates to a construction method of assembling dual-tubular oozing water blind groove and a path base seepage water structure.Background technique[0002]The road is in a belt form, often requires across a variety of complex hydrogeological environments, or even a variety of climate environments, and the performance of road street roads will be affected by factors such as soil physical mechanical properties, terrain landforms, formation conditions, water and temperature. . In order to ensure the long-term stability of the road, in the roadbed road design, it is generally designed to design corresponding response engineering measures, in which the roadbed stream filled strength reduction and the filling layer softening deformation in order to solve the development of groundwater development and the filling layer softening caused. Some problems such as cracking of road ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E03F3/04E03F5/14E01C11/22
CPCE01C11/227E03F3/04E03F5/14
Inventor 石晓娜
Owner CHENGDU UNIVERSITY OF TECHNOLOGY